Settlement of Red Mountain Claims Dispute
Released
Released
Announcement PDF
13 May 2024
SETTLEMENT OF DISPUTE AT RED MOUNTAIN PROJECT, USA
Astute maintains ownership of full surface area of Red Mountain Project
Key Highlights
•
Red Mountain claims dispute now settled, with Astute
to acquire competitor claims.
•
Maiden Red Mountain drilling campaign now scheduled to
commence in the week of 20 May 2024.
•
Agreement with the University of Alberta to supply lithium
clay samples for the development of innovative lower-cost
and environmentally friendly lithium extraction.
•
Additional ‘extension’ claims staked along the southwestern margin of the Red Mountain Project.
Astute Metals NL (ASX: ASE) (“ASE”, “Astute” or “the Company”) is pleased to advise it has entered into a
binding settlement with Rubicon, the owner of competing claims at its Red Mountain Lithium Project in
located in the highly prospective lithium claystone district of Nevada, USA.
Under the terms of the settlement, the Company has agreed to pay Rubicon $US75,000 on signing and
a further $US75,000 in 12 months. The detailed terms of the settlement are confidential and reflect
no admission of liability by either party.
The settlement represents an excellent outcome for the Company, providing certainty of tenure over the
whole of the Red Mountain Property, an updated map of which is shown in Figure 1.
Astute Chairman, Tony Leibowitz, said:
“We are delighted to have finally secured a settlement, allowing us to move forward with the
exploration of this exciting lithium claystone asset. The settlement of the dispute means that Astute
now has ownership of the full surface area at Red Mountain, clearing the way for us to unlock the
value of the Project. Our maiden drill program at Red Mountain is imminent, with the allocated rig
expected to be on site next week and drilling operations scheduled to begin shortly thereafter. This
is an exciting time for our lithium exploration program in Nevada.”
Maiden Drilling Campaign Update
The full rebuild of the rig allocated for the Red Mountain campaign is approaching completion (see
Figure 2). Accordingly, the maiden drilling campaign at Red Mountain has a revised commencement,
with the rig expected to arrive on site and start drilling during the week commencing 20 May 2024.
The campaign will comprise a total of 10 drill sites for approximately 1,500m/5,000ft, subject to ground
conditions encountered and rock types intersected during initial drilling. The planned drilling covers a
wide strike of the observed lithium-in-soil anomaly, with holes testing strategic points over a 5km northsouth extent, with an objective to test for thickness and grade of lithium mineralisation in the subsurface1.
The planned drilling will provide the Company with an excellent understanding of the potential of the Red
Mountain Project to host a significant lithium clay deposit.
University of Alberta Collaboration
The Company has executed an agreement with the University of Alberta (‘UoA’) for a collaboration
project studying methods of extracting lithium from clay, with the objective of developing lower-cost and
environmentally friendly processing methods.
Suite 6, Level 5, 189 Kent St, Sydney NSW 2000 | GPO Box 2733, Sydney NSW 2001
+61 (0) 2 8046 2799 | admin@astutemetals.com
www.astutemetals.com
Under the agreement, the Company will provide lithium-bearing clay samples from its Projects, and UoA
will undertake mineralogy and extraction testwork on the samples, at no cost to Astute. This work forms
part of a PhD study being undertaken at UoA, and positive outcomes from the collaboration may assist
the Company in advancing its Nevada lithium projects in due course.
The Company intends to supply samples from its recent drilling at the Altair Project as well as samples
from the imminent drilling program at Red Mountain.
Figure 1. Permitted drill hole locations and gridded lithium soil geochemistry rock chip samples at Red Mountain,
showing the recently staked Red Mountain Extension area.
Additional Claims Staked
The Company has staked an additional 102 claims on the south-western boundary of the Red Mountain
Project.
This new claim area, named Mountain Extension’, abuts a zone of strong lithium-in-soil anomalism which
may have further potential for lithium mineralisation. It is located on a Wilderness Study Area that has
been recommended for return to multiple uses (which may allow ground disturbing exploration) by the
Federal Bureau of Land Management, however this requires an act of Congress in order to be effected.
The Company has staked this ground with a view that, should exploration drilling at Red Mountain result
in the discovery of a lithium deposit, the extension claims may contain an along-strike extension of such
a deposit. The Company will seek to advance the Red Mountain Extension area if and/or when this occurs.
The location of the new claims area is shown as a shaded grey polygon in Figure 1.
Suite 6, Level 5, 189 Kent St, Sydney NSW 2000 | GPO Box 2733, Sydney NSW 2001
+61 (0) 2 8046 2799 | admin@astutemetals.com
www.astutemetals.com
Figure 2. Workshop re-assembly of the Reverse-Circulation drill rig ahead of its mobilization to Red Mountain.
Kibby Basin
The Kibby Basin Project area abuts Belmont Resources’ (TSX-V: BEA, ‘Belmont’) lithium brine project, and
was originally located on the basis of the prospectivity of the adjacent Belmont Project 2. Subsequent
exploration drilling by Belmont and then JV Partner Marquee Resources (ASX: MQR) resulted in the
identification of only weak lithium concentrations in brine and low-level lithium clay mineralisation,
neither of which are considered by Astute to have ultimate economic potential.
Following a review by the Company, this lack of prospectivity is considered to extrapolate to the Kibby
Basin Project area and, in light of this, the Company has decided that it will not undertake any further
investment in exploration on this Project area.
1 ASX: ASE 28 March 2024 ‘Astute gears up for maiden drilling campaign at Red Mountain Lithium Project, USA’
2 ASX: ARO 1 June 2022 ‘Astro secures highly prospective US lithium project and 80% interest in Australian IOCG project’
Authorisation
This announcement has been authorised for release by the Board of Astute.
More Information
Matt Healy
Executive Director
mhealy@astutemetals.com
+61 (0) 431 683 952
Nicholas Read
Media & Investor Relations
nicholas@readcorporate.com.au
+61 (0) 419 929 046
Competent Persons
The information in this report is based on information compiled by Mr Matthew Healy, a Competent
Person who is a Member of The Australasian Institute of Mining and Metallurgy (AusIMM Member number
303597). Mr Healy is a full-time employee of Astute Metals NL and is eligible to participate in a Loan
Funded Share incentive plan of the Company. Mr Healy has sufficient experience that is relevant to the
style of mineralisation and type of deposit under consideration and to the activity being undertaken to
qualify as a Competent Person as defined in the 2012 Edition of the ‘Australasian Code for Reporting of
Exploration Results, Mineral Resources and Ore Reserves’. Mr Healy consents to the inclusion in the report
of the matters based on his information in the form and context in which it appears.
Suite 6, Level 5, 189 Kent St, Sydney NSW 2000 | GPO Box 2733, Sydney NSW 2001
+61 (0) 2 8046 2799 | admin@astutemetals.com
www.astutemetals.com
Share your feedback