Globally Significant Maiden Mineral Resource Estimate of
3Mt Contained Lithium-Carbonate Equivalent for Red
Mountain Lithium Project, Nevada, USA
Exceptional maiden inferred MRE establishes Red Mountain as one of the most
significant new lithium developments in North America
Highlights
• Maiden Inferred Mineral Resource Estimate (MRE) for the Red Mountain Lithium Project of
500Mt @ 1,139ppm Li for 3.03Mt contained Lithium Carbonate Equivalent (LCE)27
reported
above the preferred 700pm Li cut-off grade, comprising;
o Red Mountain North - 91.6Mt @ 1,618ppm Li for 0.79Mt LCE, including a high-grade
component of:
▪ 47.9Mt @ 2,193ppm Li for 0.56Mt LCE at a 1,300ppm Lithium cutoff
o Red Mountain Central - 408Mt @ 1,031ppm Li for 2.24Mt LCE at a 700ppm Lithium
cutoff
• Mineralised rocks outcrop at surface and are open at depths of >250m below surface
• Red Mountain is situated in the world’s premier mining jurisdiction of Nevada, which is home
to advanced sedimentary lithium deposits such as Thacker Pass (NYSE: LAC)25
and Rhyolite
Ridge (ASX: INR)30
• Serviced by high-quality infrastructure, the Project is located immediately adjacent to Route 6,
between mining the hubs of Ely and Tonopah, 20km west of the ‘Nevada One’ 525kV
transmission line, and with substantial secured private water rights.
• There is outstanding potential to grow the Mineral Resources with significant drill intersections
and high-grade surface samples sitting outside of the MRE extents and with mineralisation
open along strike and at depth
• Venari now ranked as one of the larger lithium explorers on the ASX, on a contained Lithium
Carbonate Equivalent (LCE) basis. (See Figure 3 and Table 2 for breakdown of compared
MREs)
• Revised Red Mountain Exploration Target to be announced later this month
• Exploration Plan of Operations submitted to the Bureau of Land Management to allow for
expanded exploration drilling activities under expedited Trump Administration provisions28
.
• Delivery of the maiden MRE comes as lithium prices continue their resurgence, with the
Shanghai Metal Market Battery-Grade Lithium Carbonate Prices more than doubling over the
past three months from $10,000 to $20,388 USD/t31
2
newmurchgold.com.a
Venari Chief Executive Officer, Matthew Healy, said:
“The delivery of this standout maiden resource is a huge milestone for Venari, immediately propelling
the Company to the forefront of ASX lithium explorers and establishing Red Mountain as one of the
largest new lithium resources in the Americas and a compelling development opportunity.
“Red Mountain exhibits all the key characteristics that we look for in a large-scale mineral asset – scale,
extensivemineral endowment, and an accessible high-grade zone that can be targeted for initialmining.
In addition, metallurgical test-work has demonstrated an economic pathway to recover the metal, and
the project is located in a Tier-1 mining district close to world-class infrastructure.
“This puts both Venari Minerals and Red Mountain firmly on the map of significant North American
lithium projects and gives us an incredible foundation to advance the Project quickly to the next stage,
not only by growing and upgrading the MRE through further drilling, but also by initiating development
studies at an extremely favourable time in the metals cycle and in a period when there is strong US
policy momentum to support the development of new domestic critical minerals asset.”
Venari Chairman, Tony Leibowitz, added:
“To advance the RedMountain Lithium Projectfromdiscovery hole to maidenMineral Resource in under
two years is a remarkable achievement. With this impressive maiden MRE, investors finally have the
opportunity to see the enormous value in this discovery and the benefits of the counter-cyclical strategy
we have been pursuing for the past two years.
“Venari now owns one of the larger exploration-phase lithium resources on the ASX. And it has
enormous potential for growth – being limited only by the extent of drilling, with clear potential along
strike, at depth and at a number of locations well beyond the current MRE.
“I would like to congratulate the team on achieving this milestone. We now have a substantial platform
to build a significant mining company, underpinned by one of the largest new lithium resources in North
America – one that is strongly aligned with the Trump Administration’s goal of rapidly increasing
domestic production of key critical minerals. We are looking forward to rapidly advancing the Project to
the next phase.”
Venari Minerals NL (ASX: VMS) (“Venari”, “the Company” or “VMS”) is pleased to announce a maiden
Mineral Resource Estimate (MRE) for its 100%-owned flagship Red Mountain Lithium Project located in
Nevada, USA.
The maiden MRE for Red Mountain has been delivered less than two years since the discovery hole was
drilled into the deposit in May 20241
. Since that time, the Company has rapidly advanced the project,
adopting a counter-cyclical approach to its exploration at a time of weakness in the lithium market.
With the lithium industry now undergoing a strong resurgence, the delivery of this substantial new MRE
has confirmed Red Mountain a significant deposit in the USA with potential to become a valuable new
long-life source of lithium aligned with Western supply chains.
Unlike most other sedimentary lithium deposits, the Red Mountain Project stratigraphy dips gently to
the east, which results in outcropping, or shallowly subcropping, mineralised rocks. The thickness of
the mineralised zones, the presence of high-grade mineralisation >2,000ppm Li in the Project north,
together with their outcropping character, bodes well for any future assessment of project economics.
3
newmurchgold.com.a
The maiden Red Mountain Mineral Resource Estimate is provided below:
Area Category Tonnes (Mt) Li (ppm) LCE (%) LCE (Mt)
North Inferred 91.6 1,618 0.86% 0.79
Central Inferred 408 1,031 0.55% 2.24
TOTAL Inferred 500 1,139 0.61% 3.03
Table 1. Red Mountain maiden MRE at the preferred reporting cut-off grade of 700ppm Li.
MRE reported under a range of cut-off grades in Table 3.
Figure 1. Location of Red Mountain and other Nevada Lithium projects.
4
newmurchgold.com.a
Project Background
The Red Mountain Lithium Project is a virgin discovery made by the Company, the result of a Q1 2023
project generation exercise and subsequent field reconnaissance by Venari’s in-house technical team
that identified highly mineralised lithium clays at surface27
. Consequently, the Project was staked in
August 2023 and a project-wide soil sampling grid conducted shortly thereafter, which identified large-
scale lithium anomalism in soils over an 8km strike26
.
The Project area has broad mapped tertiary lacustrine (lake) sedimentary rocks known locally as the
Horse Camp Formation23
.Elsewhere in Nevada,equivalent rocks host large lithium deposits (see Figure
1) such as Lithium Americas’ (NYSE: LAC) 66.7Mt LCE Thacker Pass Project25
and American Battery
Technology Corporation’s (NASDAQ: ABAT) 18.7Mt LCE Tonopah Flats deposit26
.
Follow-up rock chip sampling identified further outcropping lithium-mineralised rocks justifying the
first drilling campaign in May 2024. The discovery hole, RMRC001, intersected 59.4m @ 1,300ppm Li1
,
indicating that the discovery had excellent potential to be higher grade than most sedimentary lithium
deposits in the USA.
The Company conducted a further three drilling campaigns over the subsequent 22months, with a total
of 30 of 32 drill holes intersecting lithium mineralisation1-14
.
In parallel, the Company rapidly advanced metallurgical test-work, with scoping-level leachability
demonstrating that the lithium is highly leachable (up to 98% lithium leachability), and beneficiation
test-work revealing mineralisation has excellent character for removal of gangue minerals while
retaining valuable lithium-bearing clays and reducing acid-consumption15-19
.
Outside of the technical realm, in 2025 the Company filed an Exploration Plan of Operations with the
Bureau of Land Management in order to expand the exploration disturbance footprint beyond the
standard 5-acres afforded by notice-level approvals, and secured a 113-acre acre private property with
substantial annual water rights as a strategic investment in the Project’s future28,29
. The Red Mountain
project is well-serviced by infrastructure, being located immediately adjacent to the transcontinental
Route 6 and 20km west of the 525kV ‘One Nevada’ high-voltage transmission line and with 592,000m3
of annual water rights secured associated with only 6km from the Project29
(Figure 2).
5
newmurchgold.com.a
Figure 2. Red Mountain lithium Project, proximal road and electrical transmission infrastructure,
Nye and White Pine County border and secured private property with associated water rights.
6
newmurchgold.com.a
Comparison with other ASX-listed Exploration-Phase Lithium Mineral Resources
The Red Mountain Lithium Project compares favourably with other ASX-listed companies’ Lithium
MREs on the basis of contained Lithium (Figure 3, Table 2). While the Red Mountain MRE is currently
comprised wholly of inferred category Mineral Resources, in contrast with other exploration-phase
MREs which are largely dominated by higher confidence Indicated-category Mineral Resources, the
Company intends to actively pursue infill drilling with a view to upgrading the Inferred MRE to higher
category Indicated status and, potentially, Measured Resources following further exploration drilling to
be conducted in 2026.
Figure 3. ASX-listed lithium explorer (producers and developers excluded) ranked by contained Lithium Carbonate
Equivalent (LCE) by Mineral Resource Category and deposit type. Contained LCE calculated using 2.475 conversion
factor for Li2O – LCE and 5.323 conversion factor for ppm Li to LCE. Source MRE details provided in Table 2
0
5
10
15
20
25
Li
in
Combined
MRE
(LCE,
Mt)
Red Mountain
Lithium Project
7
newmurchgold.com.a
Company, Ticker, Resource type Mineral Resource Estimates
LCE in Mineral Resources
(Mt)
Measured Indicated Inferred Meas. Ind. Inf. Total
Jindalee Lithium, JLL, Sed.
1470Mt @
1420ppm Li
1540Mt @
1270ppm Li
11 10 21.5
Lake Resources, LKE, Brine
4.19Mt LCE @
226.4mg/l Li
4Mt LCE @
206.6mg/l Li
2.89Mt LCE @
215mg/l Li
4.19 4.00 2.89 11.07
European Metal Holdings, EMH,
Spod.
53.3Mt @
0.48% Li2O
360.2Mt @
0.44% Li2O
294.7Mt @
0.39% Li2O
0.63 3.92 2.84 7.40
Pmet, PMT, Spod.
108.68Mt @
1.41% Li2O
35.08Mt @
1.35% Li2O
3.80 1.17 4.97
Prairie Lithium, PL9, Brine
4.6Mt LCE @
98mg/l Li
4.60 4.60
Venari Minerals, VMS, Sed.
500Mt @
1,139ppm Li
3.03 3.03
Winsome Resources, WR1, Spod.
61.4Mt @
1.14% Li2O
16.5Mt @
1.19% Li2O
1.73 0.49 2.22
Wildcat Resources, WC8, Spod.
70Mt @ 1.01%
Li2O
4.1Mt @
0.76% Li2O
1.75 0.08 1.83
Global Lithium Resources, GL1,
Spod.
36.7Mt @
1.03% Li2O
32.9Mt @
0.96% Li2O
0.94 0.78 1.72
Atlantic Lithium, A11, Spod.
3.7Mt @
1.37% Li2O
26.1Mt @
1.24% Li2O
7Mt @ 1.15%
Li2O
0.13 0.80 0.20 1.13
Pursuit Minerals, PUR, Brine
0.59Mt LCE @
515.1mg/l Li
0.51Mt LCE @
495.4mg/l Li
0.59 0.51 1.10
Greenwing Resources, GW1, Brine
0.67Mt LCE @
192mg/l Li
0.4Mt LCE @
200mg/l Li
0.67 0.40 1.07
Delta Lithium, DLI, Spod.
0.5Mt @ 1.2%
Li2O
23.3Mt @
1.09% Li2O
12.9Mt @
1.01% Li2O
0.01 0.63 0.32 0.97
Green Technology Metals, GT1,
Spod.
16.1Mt @
1.29% Li2O
14.2Mt @
1.01% Li2O
0.51 0.35 0.87
Infinity Metals, INF, Spod.
59Mt @ 0.29%
Li2O
52.2Mt @
0.27% Li2O
0.42 0.35 0.77
European Lithium, EUR, Spod.
4.31Mt @
1.13% Li2O
5.43Mt @
0.95% Li2O
3.14Mt @
0.9% Li2O
0.12 0.13 0.07 0.32
Critical Resources, CRR, Spod.
8Mt @ 1.07%
Li2O
0.21 0.21
Lithium Plus Minerals, LPM, Spod.
0.42Mt @
1.22% Li2O
3.67Mt @
1.45% Li2O
0.01 0.13 0.14
Anson Resources, ASN, Brine
0.02Mt LCE @
93.5mg/l Li
0.08Mt LCE @
93.5mg/l Li
0.02 0.08 0.10
Table 2. ASX-listed lithium explorer (i.e. producers and developers excluded) Mineral Resource Estimates and contained
Lithium Carbonate Equivalent (LCE). Brine Resources as contained LCE and Li as mg/L, sedimentary resources in Mt
and ppm Li and spodumene resources in Mt and Li2O%. Contained LCE calculated from source Mineral Resource
Estimates using 2.475 conversion factor for Li2O – LCE and 5.323 conversion factor for ppm Li to LCE
Mineral Resource Estimate Sources:
ASX: LKE Noosa Mining Conference Presentation, 11 Nov 2025 ASX: JLL McDermitt PFS, 19 Nov 2024
ASX: EMH Transitional Annual Report 2024, 31 Mar 2025 ASX: PMT Corporate Presentation, Dec 2025
ASX: WR1-LiFT Corporate Presentation, 15 Dec 2025 ASX: LPM AGM Presentation, 27 Nov 2024
ASX: A11 Annual Report 2025, 11 Sept 2025 ASX: INF Annual Report 2025
ASX: GW1 AGM Presentation, 25 Nov 2025 ASX: DLI AGM Presentation, 27 Nov 2025
ASX: GT1 Investor Presentation, 10 Sept 2025 ASX: ASN AGM Presentation, 26 Nov 2025
ASX: EUR Wolfsberg Project Updated presentation, May 2022 ASX: WC8 Annual Report 2025, 23 Sept 2025
ASX: CRR NZ Gold and Antimony Projects Presentation, 6 Aug 2025 ASX: GL1 Annual Report 2025, 29 Oct 2025
ASX: PUR Resources Rising Stars Presentation, 17 Sept 2025 ASX: PL9 Annual Report 2025, 26 Sept 2025
8
newmurchgold.com.a
Exploration Upside
The Red Mountain Project offers excellent exploration upside outside of the extents of the maiden MRE.
A systematic 400m x 100m spaced soil sampling campaign conducted shortly after the project was
staked, and a series of subsequent targeted rock-chip sampling campaigns, have revealed strong
lithium-in-soil anomalism reinforced by lithium mineralisation in underlying bedrock19-24
. Figure 4
highlights a number of future drill targets outside of the wireframed MRE domains (shown in pink),
including:
• A cluster of mineralised rock chip samples with grades of up to 2,230ppm Li overlaying a
moderate 1km x 0.5km lithium in soil anomaly, located east of the MRE extents.
• A large, approximately 1.5 x 1.5km, zone of soil anomalism reinforced by high-grade rock chips
of up to 2,100ppm Li, located west of the MRE extents.
• Two zones of approximate 1km x 1km dimensions of elevated lithium in soils located
immediately south and east, respectively, of the southern terminus of the MRE.
• A substantial 2.1km-long zone of lithium in soil anomalism at the Red Mountain Extension
claim block, with a traverse of rock chip samples with lithium grades of up to 2,690ppm Li.
• Slightly elevated lithium in soils and rock chips in the 950m gap in drilling between the
northern and southern zones of the MRE.
The Company considers that each of these target areas has potential for further lithium mineralisation
which may represent potential upside to the maiden MRE. Work is currently underway on a revised
JORC compliant Exploration Target encompassing these areas, which is expected to be published
before the end of February 2026.
Next Steps
The Venari technical team is currently designing the next round of drilling for the Red Mountain Project,
which is anticipated to include infill drilling and extensional drilling, with a view to upgrading resource
category from Inferred to Indicated and, possibly some, Measured, and expanding the Resource. In
addition, the team will undertake exploration drilling to test further drill targets and identify new zones
of mineralisation for the exploration-resource pipeline. The Company intends to update the market with
firmer drilling plans by the end of the current quarter.
In 2025 the Company filed an Exploration Plan of Operations (EPO) with the Bureau of Land
Management (BLM)28
. Once approved, the EPO will increase the disturbance allowance of the Red
Mountain Project. Approval of the EPO is expected to align broadly with the commencement of the field
season.
Separately, the Company is advancing metallurgical test-work for the Red Mountain Project. With
lithium carbonate product test-work underway and results expected by the end of February, and the
recent engagement of highly-regarded engineering consultants Pitch Black Group, the Company is well
placed to advance the Project to a scoping-level flowsheet19
.
In the interim, additional campaigns of surface sampling will be undertaken to identify new zones of
lithium-bearing rocks within the Red Mountain Project, and the Company is considering options for
geophysical surveying to increase its understanding of the subsurface potential of the Project.
9
newmurchgold.com.a
About Lithium Carbonate Equivalent (LCE)
Unlike spodumene concentrate, which is a feedstock, Lithium Carbonate is a downstream product that
may be used directly in battery material production or converted to other battery products such as
lithium hydroxide.
Lithium Carbonate may be produced directly from lithium clay deposits, such as Lithium Americas’
(NYSE: LAC) Thacker Pass Project, which is currently under construction25
. Accordingly, results for Red
Mountain have been reported as both the standard parts-per-million (ppm) and as % Lithium Carbonate
Equivalent (LCE)27
.
Since the last quarter of 2025 the lithium market has rebounded strongly, with Shanghai Metal Market
Battery Grade Lithium Carbonate USD Price closing at US$20,388/t as of 30 January 2026, having more
than doubled over the past 3 months31
.
Figure 4. Red Mountain gridded soil geochemistry map with MRE mineralisation domains (500ppm Li wireframe) at or
immediately adjacent to surface and lithium rock chip sample geochemistry and conceptual drill target areas (dashed)
10
newmurchgold.com.a
Material Information Summary
Pursuant to ASX Listing Rule 5.8.1 Venari provides the following summary information material to
understanding of reported Mineral Resource Estimates for the Red Mountain Lithium Project.
Reasonable Prospects for Eventual Economic Extraction
The Competent Person has concluded that Mineral Resource Estimates reported for the Red Mountain
Lithium Project demonstrate reasonable prospects for eventual economic extraction, based on open-
pit optimisation using a lithium price of US$19,000/t LCE, 80% lithium recovery, conventional open-pit
mining methods, and US$10/t mining and US$30/t processing cost assumptions. This has formed the
basis for the wire-framing cut-off of 500ppm Li used to define the six mineralised domains of the MRE.
Geology and Geological Interpretation
The Red Mountain Lithium Project is located next to the unincorporated township of Currant, in Nye
County Nevada, immediately east of the Railroad Valley. The Railroad Valley is one of numerous valleys
separated by mainly north-south trending mountain ranges as part of the Western US ‘Basin and Range’
physiographic region. Basin and Range topography was produced through an extensional tectonic
regime in operation over the Miocene to present day (i.e. the last 20 million years) which has resulted in
uplift of ancient bedrock and the development of deep basins filled with alluvium sourced from
weathering of the proximal range rocks.
The Red Mountain Lithium Project is hosted by the Horse Camp Formation, a Miocene-aged sequence
half-graben basin the uppermost sequence of which comprises lacustrine rocks which host lithium-
bearing clay minerals in part. Lithologies grade from muddy matrix boulder debrites deposited on
subaerial alluvial fans, in the extremities of the basin, to rhythmic shallow water conglomerate and
sandstone deposited on a fan delta top to turbidites and siltstone deposited offshore on the delta front
and deep lacustrine environment.
Clay-bearing lithologies include sandstone and siltstone, with lesser fine-grained sediments. Clay
forms part of the cement, along with calcite, in most cases weakly binding silt to gravel sized particles
within the various lithologies. Formal claystones are rare in the drilled parts of the Horse Camp Basin.
These lithologies display a general north-south strike and easterly dip (Figure 6), with some variation as
a function of a structural trough in the centre of the basin (Figure 5). A total of 781 strike and dip
measurements taken at the project constrain the stratigraphic controls at surface. Recent alluvial is
present as a typically thin veneer over subcropping lacustrine rocks in the northern and central parts of
the project (Figure 5)
Lithium mineralisation is associated only with clay mineralogy, and only a single clay mineral –
Hectorite [Na₀.₃(Mg,Li)₃Si₄O₁₀(F,OH)₂] – has been identified to date in mineralogical analysis of samples
from the Project18
.
11
newmurchgold.com.a
Figure 5. Red Mountain chronostratigraphic geology map with structural measurement locations and
mineralisation domains (500ppm Li wireframe) at or immediately adjacent to surface.
12
newmurchgold.com.a
Figure 6. Cross-section through drill-holes RMDD003 and RMRC013 demonstrating eastward dipping
lacustrine stratigraphy downhole lithium geochemistry and surface rock-chip lithium geochemistry.
Classification Criteria
The current Mineral Resource is classified as Inferred, based on the spatial distribution of the drill holes
and the distribution of the assay data. They preclude assignment of measured and indicated resource
classification at this point. The proposed 2026 drilling campaign will provide stronger support for
classifying the resource at higher certainties.
Cut-Off Grade
The wire-framing cut-off grade and the lowest MRE block reporting cut-off is 500ppm Li, which is based
on a Lithium Carbonate price of $19,000 USD/t, mining and processing costs of $10 and $30 per tonne,
respectively, and a lithium recovery of 80%.
The project total MRE at a preferred reporting cut-off of 700ppm Li is 500Mt at an average lithium grade
of 1,139ppm Li. The MRE, divided into the Norther and Central domains, and reported by various block
cut-off grades is tabulated below, illustrating potential scalability of Red Mountain as either a larger
tonnage lower-grade project, or low tonnage higher-grade project.
13
newmurchgold.com.a
Area Category
Cut-off
(ppm Li)
Tonnes
(Mt)
Li
(ppm)
LCE (%)
Contained
LCE (Mt)
North Inferred 500 113 1427 0.76% 0.85
North Inferred 700 91.6 1618 0.86% 0.79
North Inferred 900 77.8 1765 0.94% 0.73
North Inferred 1100 60.3 1988 1.06% 0.64
North Inferred 1300 47.9 2193 1.17% 0.56
North Inferred 1500 38.2 2395 1.27% 0.49
North Inferred 1700 30.0 2614 1.39% 0.42
Central Inferred 500 563 912 0.49% 2.73
Central Inferred 700 408 1031 0.55% 2.24
Central Inferred 900 266 1157 0.62% 1.64
Central Inferred 1100 145.6 1295 0.69% 1.00
Central Inferred 1300 66.0 1427 0.76% 0.50
Central Inferred 1500 20.3 1572 0.84% 0.17
Central Inferred 1700 3.9 1765 0.94% 0.04
Total Inferred 500 675 998 0.53% 3.59
Total Inferred 700 500 1139 0.61% 3.03
Total Inferred 900 344 1295 0.69% 2.37
Total Inferred 1100 206 1497 0.80% 1.64
Total Inferred 1300 114 1749 0.93% 1.06
Total Inferred 1500 58.5 2109 1.12% 0.66
Total Inferred 1700 33.9 2516 1.34% 0.45
Table 3. Red Mountain MRE at various cut-off grades
Notes
• Mineral Resources are not mineable Reserves and economic viability has not been demonstrated
• There is no guarantee that any of the reported Mineral Resources will convert to Mineral Reserves
• The Mineral Resource Estimate has been prepared by Competent Person Richard Newport, principal
partner of Richard Newport & Associates – Consultant Geoscientists.
• Headline Mineral Resource Estimates are shown in bold text
• Wireframe cut-off grade and lowest block reporting cut-off grade of 500ppm is based on mining and
processing costs of $10 and $30 per tonne, respectively, a Lithium Carbonate price of $19,000 and 80%
recovery
• Mineral Resources assume open-pit mining to a nominal maximum depth of 200m below surface
• Lithium Carbonate Equivalent has been calculated from Lithium parts-per-million (ppm) by the formula
LCE (%) = Li (ppm) x 5.323 /10,000
• Reported figures are rounded and therefore may not sum to totals
14
newmurchgold.com.a
Hole ID Hole Type
East
(NAD83)
North
(NAD83)
RL
(NAVD88)
Dip
(°)
Azimuth
(°)
RMDD001 Diamond 637546.1 4286147.4 1718.5 -50 270
RMDD002 Diamond 637186.7 4290569.6 1709.9 -50 270
RMDD003 Diamond 637127 4291198 1707.8 -50 269
RMDD004 Diamond 637593 4289988 1733.3 -50 268.5
RMDD005 Diamond 637290 4287427 1706.3 -50 269
RMDD006 Diamond 637341 4288618 1719.7 -50 265.5
RMDD007 Diamond 637327 4288197 1707.7 -50 269.5
RMDD008 Diamond 637516 4286902 1724.1 -50 265.5
RMRC001 RC 637610.2 4285588.8 1732.2 -50 179.5
RMRC002 RC 637104.6 4290200.8 1723.8 -50 270.5
RMRC003 RC 637104.6 4290200.8 1723.8 -90 -
RMRC004 RC 637782.2 4288743.1 1731.4 -50 270.5
RMRC005 RC 637320.8 4288194.4 1707.7 -50 270.5
RMRC006 RC 637534.4 4288196.7 1720.3 -50 271
RMRC007 RC 637099.9 4287805.5 1695.1 -50 270.5
RMRC008 RC 637676.5 4286217.9 1728.8 -50 270
RMRC009 RC 637667.3 4285794.8 1729.5 -50 271.5
RMRC010 RC 636942.4 4285791.4 1700.6 -50 270.5
RMRC011 RC 636423.1 4286202.5 1676.1 -50 271.5
RMRC012 RC 637010.3 4291916.6 1705.5 -50 266.5
RMRC013 RC 637122 4291198.1 1707.7 -70 90.5
RMRC014 RC 637192.5 4290568.7 1710.2 -50 270.5
RMRC015 RC 637183.1 4290570.6 1709.9 -75 90.5
RMRC016 RC 637019.9 4291604.7 1703.7 -50 270.5
RMRC017 RC 637023.2 4291604.7 1704.0 -90 -
RMRC018 RC 637266.1 4289961.9 1728.5 -70 270.5
RMRC019 RC 637892.1 4288689.1 1736.2 -50 270.5
RMRC020 RC 637672.3 4288761.1 1728.1 -50 270.5
RMRC022 RC 637532.1 4288202.5 1720.4 -90 -
RMRC023 RC 637420.9 4288217.3 1713.3 -50 270.5
RMRC024 RC 637495.2 4287762.7 1723.8 -50 270.5
RMRC025 RC 637239.8 4287748.1 1705.3 -60 270.5
Table 4. Red Mountain drill collar details
15
newmurchgold.com.a
Drilling Techniques
A total of 32 drill-holes have been completed at the Red Mountain Project (Table 4) in four drilling
campaigns1-14
. A tabulated summary by drilling type is provided in Table 5.
Campaign Type Collars Feet Metres
May 2024 RC 11 4,980 1,517.9
October 2024 Diamond 2 1,400 426.7
April 2025 Diamond 6 4,566 1,391.7
October 2025 RC 13 8,790 2,679.2
TOTALS - 32 19,736 6,015.6
Table 5. Red Mountain exploration drilling summary
Reverse Circulation
Reverse Circulation (RC) drilling employed a 5.5” hammer bit, or tricone bit, with a cross-over sub
immediately behind the hammer. Drilling was conducted wet, with injected drill fluids to transport drill
cuttings to the surface through drill rods, as is standard practice in the USA. RC drilling conducted in
May 2024 was undertaken by Harris Drilling and in October 2025 by Major Drilling.
No downhole surveys were taken on the maiden drilling campaign holes, while the October 2025
campaign holes were surveyed using a north-seeking Gyro.
Diamond Drilling
Diamond Drilling (DD) employed conventional HQ (April 2025) and triple-tube HQ coring (October
2024). Both diamond drilling campaigns were conducted by True North Drilling. All diamond drill-holes
were surveyed down-hole using a north seeking Gyro.
Sampling and Sub-Sampling Techniques
Samples from the aforementioned RC and Diamond drilling campaigns were transported to ALS
analytical laboratories in Reno or Elko by Venari staff and contractors. Sampling and sub-sampling
techniques employed are described below.
Reverse Circulation
RC samples were collected on a 5-foot (approx. 1.5m) basis throughout the hole, with drill cuttings
passing through a rotating cone splitter ahead of collection. Depending on the drill campaign, either
30% (October 2025) or 50% (May 2024) of the drilled sample was collected in a calico bag, which was
then air dried on elevated grid-mesh racking for approximately 5 days before being transported to ALS
laboratories in Elko or Reno.
Diamond Drilling
Drill core was sampled to nominal 5-foot sample lengths or to geological boundaries. Drill core was
transported to a third-party facility in Elko, Nevada, for photography, bulk density measurements and
core cutting. Core was cut in half down the core axis, with one side of the cut core placed in a calico
bag and despatched to ALS laboratories in Elko. The remaining core was retained for reference or for
other purposes such as metallurgical test-work.
16
newmurchgold.com.a
Figure 7. Red Mountain (down-hole) drill intersections over gridded soil geochemistry image and
mineralisation domains (500ppm Li wireframe) at or immediately adjacent to surface
17
newmurchgold.com.a
Estimation Methodology
The following Estimation Methodology was employed for the Red Mountain Lithium Project.
Microsoft Excel Spreadsheet software was used to import raw assay data received from ALS
laboratories and spatial and geological drill-hole information provided by the Company to the
Competent Person.
QA/QC assessment was performed on the above data including a site visit in September/October 2025
by the Competent Person to verify the existing data. No discrepancies were observed. The raw data was
imported from the spreadsheets into MicroMine 2011 (Version 12.5) and updated as required. The last
updates were early January 2026, which completed the drill-hole assay data set from all four drilling
campaigns.
Examination of all the drilling plots in plan and sections revealed both a strongly consistent strike and
dip of the sediments hosting elevated Lithium assays, and distinct, persistent zones of greater than
500ppm Lithium.
It was therefore elected to wireframe the greater than 500ppm lithium intersections into six (6)
individual wireframe domains – three in both the North and Central zones of the Project (Table 6, Figures
8 and 9). There is a significant drilling gap of approximately 950m between the zones and no attempt
was made to correlate and wireframe the two zones across this gap.
Wireframe X (East) Y (North) Down-dip
North_01 30 840 430
North_02 130 2,040 430
North_04 30 1,550 430
Central_01 310 3,550 400
Central_02 220 3,550 400
Central_03 60 1,850 400
Table 6. Mineral Resource Estimate wireframe domain dimensions (metres)
Drilling data in each wireframe was subject to statistical analysis, compositing, and proportional effect.
Reference global estimates were then