30 June 2026 Quarterly Report
Production of battery-grade 99.5% lithium carbonate and identification of strategic by-product
opportunities in strontium and magnesium positions Red Mountain for next phase of growth;
Successful $6.1m fund raising completed to underpin accelerated work programs
Highlights
Red Mountain Lithium Project, Nevada (USA)
• Battery-Grade (99.5%) Lithium Carbonate produced from the Red Mountain Lithium Project:
o Battery-grade product achieved using an established process flowsheet.
o Lithium carbonate demonstrates a low-impurity profile.
o Test-work provides proof-of-concept that the Red Mountain mineralisation can be
processed into a value-added lithium product.
o Potential by-products identified in magnesium sulfate (Epsomite) and Strontium, used
in agricultural and defence-related markets, with US import-dependence rates of 59%
and 100% respectively.
o Strontium has been declared a Strategic Material by the US Department of War due to
its pyrotechnic utility in tracer ordnance and flares.
o Magnesium is a US Department of Energy Critical Mineral, with the use of the
compound Epsomite representing a rapidly growing market.
o Venari’s systematic strategy to create value from by-products includes:
▪ Metallurgical testing to extract by-products from leachate and/or residues;
▪ Addition of strontium and magnesium to the Red Mountain Mineral Resource
Estimate; and
▪ Targeting US Government support for grant funding and fast-tracked permitting.
• In-fill drilling permitted paving the way for the Company to rapidly advance the project:
o The Bureau of Land Management (BLM) approved a further six drill sites at the project.
o Next phase of drilling is designed to in-fill the high-grade northern end of the Red
Mountain Project to upgrade the Mineral Resource Estimate (MRE) from Inferred to the
higher-confidence Indicated category, in accordance with the JORC (2012) Code.
o The Company intends to a focus on the high-grade northern zone initially, which is
expected to form the foundation of a Scoping Study, targeted for completion in Q1 2027.
o The Company’s Exploration Plan of Operations (EPO) remains in progress.
Corporate
o Highly successful $6.1 million capital raising subsequent to quarter-end, allowing the
Company to progress the next phase of work at Red Mountain, culminating in a
Scoping Study.
o Sale of the Georgina Basin IOCG asset results in a simplification of the Company’s
asset base, allowing it to concentrate on the flagship Red Mountain Lithium Project.
Sale realized $0.67 million and reduces the Company’s ongoing holding costs.
2
newmurchgold.com.a
Venari Minerals NL (ASX: VMS) (“Venari”, “the Company” or “VMS”) is pleased present its activities for
the quarter ended 30 June 2026.
Red Mountain Lithium Project, Nevada
The Red Mountain Project area has broad mapped tertiary lacustrine (lake) sedimentary rocks known
locally as the Horse Camp Formation. Elsewhere in Nevada, equivalent rocks host large lithium
deposits (see Figure 1) such as Lithium Americas’ (NYSE: LAC) 62.1Mt LCE Thacker Pass Project and
American Battery Technology Corporation’s (NASDAQ: ABAT) 18.7Mt LCE Tonopah Flats deposit.
A total of 32 drill holes have been completed at the project to date for a combined 6,015m of drilling
across four campaigns. These campaigns have been highly successful, intersecting strong lithium
mineralisation in almost every hole. The Red Mountain maiden Mineral Resource Estimate of 500Mt @
1,139ppm Li for 3.03Mt contained LCE (at a 700ppm Li cut-off) includes a high-grade zone in the north
of the project of 47.9Mt @ 2,193ppm Li for 569kt contained LCE, at a 1,300ppm Li cut-off.
Figure 1. Location of Venari’s Red Mountain Lithium Project and other Nevada lithium deposits.
3
newmurchgold.com.a
Scoping leachability test-work on mineralised material from Red Mountain indicates high leachability
of lithiumof up to 98%,varying withtemperature,acid strength and leaching duration,and beneficiation
test-work has indicated the potential to upgrade the Red Mountain mineralisation.
The Red Mountain project is well-serviced by infrastructure, being located immediately adjacent to the
transcontinental Route 6, 20km west of a 525kV high-voltage transmission line and a 113-acre private
property with 592,000m3
.p.a of associated water rights secured only 6km from the Project (Figure 2).
Figure 2. The Red Mountain Lithium Project is well-serviced by road and power with nearby private water rights secured.
4
newmurchgold.com.a
Work completed during the quarter
Battery-Grade Lithium Carbonate Product
During the quarter, metallurgical test-work resulted in the successful production of a 99.5% battery-
grade lithium carbonate from Red Mountain mineralised rocks.
The purpose of the test-work, undertaken by Hazen Research Inc., was to provide proof-of-concept that
lithium carbonate can be produced from the Red Mountain Lithium Project using an established
flowsheet that has been shown to be capable of producing lithium carbonate from other sedimentary-
hosted lithium projects.
The test-work was conducted using a nominal 10kg composite HQ-drill core sample from drill-hole
RMDD002 (Tables 1 and 2, Figure 3) with lithium carbonate produced through a process of sulfuric acid
leaching, neutralisation and filtration, impurity removal and lithium carbonate precipitation. The
resultant lithium carbonate was then evaluated for purity.
Hole ID From (ft) To (ft)
RMDD002 165 170
RMDD002 170 175
RMDD002 175 180
RMDD002 180 186
RMDD002 186 190.5
RMDD002 190.5 195
RMDD002 195 201.7
Table 1. Source drill-hole sample details for Lithium Carbonate test-work composite
Hole ID East (NAD83) North (NAD83) RL (m) Azimuth (°) Dip (°) Depth (m)
RMDD002 637186 4290574 1709 270 -50 182.88
Table 2. Drill collar details for RMDD002
The lithium carbonate produced has a calculated purity of 99.5%. Lithium was also analysed directly,
with a result of 99.4% Lithium Carbonate; however, the direct analysis has an expected error range of
+/- 5% (i.e. a range of 94.5 - 104.5wt% Lithium carbonate) and, as a result, convention is that the sum
total of impurities is subtracted from 100% to establish Lithium Carbonate purity.
Impurity results are provided in Table 3, along with calculated purity.
5
newmurchgold.com.a
Figure 3. Red Mountain (down-hole) drill intersections over gridded soil geochemistry image.
6
newmurchgold.com.a
Component Units Result
Na Wt% Na2CO3 0.203
Ca Wt% <0.005
SO42-
Wt% 0.0028
Cl Wt% 0.0047
Al ppm <50
Cu ppm <1
Fe ppm <50
K ppm <50
Mg Wt% MgCO3 0.288
Ni ppm <1
Zn ppm <10
Total Impurities Wt% 0.5%
Li2CO3 Calculated 99.5%
Table 3. Lithium carbonate product impurity characteristics
All analysed impurities –with the exception of sodium and magnesium – were very lowor not detectable
in the final product (Table 3).
Classification
This test-work has demonstrated the production of a battery-grade Lithium Carbonate product, where
battery-grade is ≥99.5% purity – a universally adopted industry minimum for battery-grade. Apart from
the minimum lithium carbonate purity, lithium chemicals companies (such as Livent, Albemarle or
Ganfeng) have their own specifications of what constitutes battery-grade Lithium Carbonate from the
perspective of limits of particular impurities (e.g. Cu).
In general, Lithium Carbonate produced from Red Mountain is low impurity, with most impurities not
detectable in analysis of the final product. Lower-impurity products are more attractive in the
marketplace and, as such, the Company will seek to further minimise impurities in future test-work
producing Lithium Carbonate. It is expected that sodium and magnesium can be easily reduced by
conducting the ion-exchange step earlier in the process, and/or through the targeted removal of
magnesium as Epsomite, a potentially valuable by-product.
By-product Potential
In addition, the results of the test-work identified two potentially valuable by-products – Epsomite (a
magnesium sulfate compound) and Strontium. According to Hazen Research Inc., a saleable Epsomite
product may be recovered using evaporation-cooling crystallisation. Epsomite prices in the US have
ranged from US$370-430/t in the past year, indicating a compelling incentive for the Company to further
investigate this potentially valuable by-product, particularly when the production of Lithium Carbonate
from a sulfuric leach method already necessitates magnesium removal.
7
newmurchgold.com.a
Strontium – a pyrotechnic metal used in defence applications such as for tracers in ordnance – is one
of a group of chemicals that, under the National Defense Authorisation Act 2023, will need to be
sourced domestically in the US or from select allied countries by 2028. The US is currently 100% import-
dependent for Strontium, which is present in the solid residue of mineralised material following the
sulfuric acid leach extraction of lithium. Strontium carbonate, the common processed form of
Strontium, typically commands a price of US$2,000 per tonne landed in the US, however higher purity
products can sell for over $14,000/t.
The following nominal drill intersections from the north and south of the project (Figure 1), respectively,
provide an indication of strontium and magnesium mineralisation occurring with lithium at the project:
RMRC013: 10.7m (True Width 8.6m) @ 1,670ppm Li, 4.43% Mg and 1,220ppm Sr from 57.9m
77.2m (TW 19.5m) @ 2,440ppm Li, 4.87% Mg and 4,000ppm Sr from 76.2m, including
9.1m (TW 2.3m) @ 4,750ppm Li, 9.13% Mg and 9,520ppm Sr from 102.1m, and
21.3m (TW 17m) @ 966ppm Li, 2.58% Mg and 2,370ppm Sr from 170.7m
RMDD008: 13.1m @ 972ppm Li, 1.74% Mg and 411ppm Sr from 6.7m
33.8m @ 1,130ppm Li, 2.13% Mg and 1,430ppm Sr from 34.8m
39.7m @ 859ppm Li, 1.90% Mg and 2,390ppm Sr from 102.1m
62.4m @ 1,210ppm Li, 2.29% Mg and 6,190ppm Sr from 152.2m, including
24.8m @ 1,410ppm Li, 2.57% Mg and 8,280ppm Sr from 176.7m
13.8m @ 995ppm Li, 1.98% Mg and 5,490 Sr from 224m
7.6m @ 945ppm Li, 1.57% Mg and 3,560ppm Sr from 242.3m
Mineral Phase Chemical Formula Mass (wt%)
Calcite CaCO3 38.2
Quartz SiO2 7.3
Anatase TiO2 0.2
K-Felspar (K,Na)(Si,Al)4O8 17.8
Plagioclase (Albite) NaAlSi3O8 4.3
Analcime NaAlSi2O6•(H2O) 2.6
Smectite (Hectorite) Na0.3(Mg,Li)3Si4O10(OH)2 29.6
TOTAL 100%
Table 4. Head XRD Quantitative Mineralogy results
Test-work Methodology
Samples for analysis were stage-crushed to 250µm, with head assays conducted on a 100g split ground
to 32 µm. Head assays were conducted by ICP-OES and LECO for total carbon and total sulfur (Table
5). The sample was also analysed by XRD for quantitative mineralogy (Table 4).
8
newmurchgold.com.a
Leaching was conducted using 96.5wt% sulfuric acid at 70°C and a pulp density of 20%. Kinetic
samples were taken at various times during the leach. Samples were filtered and solids washed with all
components submitted for analysis. 89% of lithium was leached during the process.
Element Assay (wt%)
Al 2.22
Ba 0.074
Ca 12.5
Fe 0.734
K 1.95
Li 0.225
Mg 4.62
Mn 0.023
Na 0.822
Sr 0.707
Ti 0.077
V 0.002
Zr 0.007
Total S 0.257
Total C 4.28
Table 5. Head assay results
Solution neutralisation was achieved using a 20wt% limestone slurry to a target pH of 6, and then the
solution was vacuum filtered to recover the lithium rich filtrate (solution) for processing. Solids were
washed with deionised water and the wash, filtrate and solids analysed.
Softening was undertaken using calcium hydroxide and sodium carbonate, respectively, to remove
magnesium and calcium from the neutralised liquor. Precipitated solids were removed using vacuum
filtration. The softened liquor was concentrated to a lithium concentration of approximately 5g/L using
evaporation and then cooled to ambient temperature to precipitate Glaubers salt (hydrated sodium
sulfate). Residual magnesium and calcium were reduced using an ion-exchange resin ahead of
crystallisation.
Crystallisation was completed in two stages. Firstly, lithium carbonate precipitation was conducted by
heating the liquor to 90°C and dosed with 25wt% Na2CO3 solution, heated to boiling and allowed to
react for 1hr to allow the lithium carbonate to precipitate. The slurry was vacuum-filtered and crystals
washed with 90°C de-ionised water and dried at 80°C. Filtrate, wash and crystals were analysed.
Second-stage precipitation was conducted by adding water to the crystallised product in a 500ml
autoclave pressurised with CO2 gas and allowed to react for 2h at ambient temperature.
9
newmurchgold.com.a
The solution was filtered to remove insoluble salts and the resultant solution boiled for 15 min to
remove CO2 and recrystallise lithium carbonate. As with the previous step, the crystals were washed
with 90°C de-ionised water and dried for analysis.
In-fill Drilling Permitted
During the Quarter, the Company completed permitting and bonding for the next round of drilling at the
Red Mountain Project. The disturbance permitted will allow in-fill drilling to be undertaken at the high-
grade northern end of the project (Figure 4), in order to upgrade this part of the MRE from Inferred to the
higher-confidence Indicated category in accordance with the JORC (2012) Code.
Figure 4. Recently permitted drill sites and previous drilling over MRE block model coloured by lithium cut-off grade.
10
newmurchgold.com.a
The upgraded MRE will underpin a Scoping Study, which is expected to yield attractive economic
parameters and highlight the Red Mountain Project as a significant US critical minerals project that may
assist in relieving US import-dependence on lithium.
The Company is currently in discussions with a number of diamond drilling contractors, with a view to
locking in a drill rig to commence the drilling as soon as practicable.
Exploration Plan of Operations
Separately, the Company continues to advance the Exploration Plan of Operations (EPO) under the
provisions of the streamlined National Environmental Policy Act (NEPA) introduced by the Trump
Administration to accelerate permitting for critical minerals projects.
The EPO, once approved by the BLM, will allow the Company to expand beyond the current 5-acre
disturbance limit imposed by Notice-level exploration permitting on Federal (public) land. The
Company expects the EPO to be approved in the coming September Quarter.
The EPO filed with the BLM contemplates a 100-acre disturbance, conducted in two phases. The first,
34-acre phase comprises a series of 17 east-west drill traverses spanning the full strike length of the
Project.
These drill traverses are 60m wide and mostly spaced at 400m intervals, providing excellent flexibility
for exploration drilling and drill spacing sufficient to support the classification of Indicated category
Mineral Resources in accordance with the JORC (2012) Code, as well as opening up additional
expansion areas, such as in the highly-prospective west of the Project, for exploration drilling.
The second phase of the EPO will open up exploration areas between the drill traverses and allow for
comprehensive in-fill drilling to be undertaken to support future feasibility-level study work.
11
newmurchgold.com.a
Needles Gold Project, Nevada
The 100%-owned Needles Project comprises 216 unpatented lode mining claims covering an area of
18km2
and lies 92km east of the mining town of Tonopah in Nye County, Nevada, USA (Figure 5). The
project was acquired due to its geological similarities with bulk-tonnage gold operations in Nevada
such as the 20Moz+ Round Mountain mine.
Figure 5. Location of Needles Gold Project and significant Nevada gold deposits.
12
newmurchgold.com.a
Previously known as the Arrowhead district, the project includes numerous historical gold-silver
workings dating from the early 1900’s to 1920’s, with some of notable scale. While historical records
are sparse, the Arrowhead Mine is recorded as an incline shaft to 350ft (106.7m) with drifting on four
levels, and the Arrowhead Extension Mine was a 150ft (45.7m) two-compartment shaft with two working
levels. These operations mined bonanza-style epithermal vein gold and silver mineralisation.
Adjacent drilling has intersected gold and silver mineralisation along strike from the shaft, including:
• Needles-63 intersected 3.42m @ 2.92g/t Au and 905g/t Ag from 25.54m
• Needles-28 intersected 6.5m @ 0.95g/t Au and 235g/t Ag from 26.2m
• Needles-27 intersected 1.4m @ 1.7g/t Au and 528g/t Ag from 31.2m
• Needles-11 intersected 1.6m @ 3.8g/t Au and 546g/t Ag from 17.6m
• Needles-7 intersected 6.1m @ 1.46g/t Au and 424g/t Ag from 26m
The current project area has seen a number of previous explorers including Newcrest (2002-04), Taranis
Resources (2002-07), Excalibur Resources (2007-09) and Greenock Resources, amongst others.
Exploration drilling conducted by Venari in 2025 successfully intersected mineralised structures,
although the tenor of gold and silver grades indicated that that deeper drilling is required. Most of the
drilling to date at the project is interpreted have only tested the high-level ‘cap’ of the system (i.e the
Kaolinite and chalcedony zones in Figure 6), with greater prospectivity deeper in the system below the
extents of drilling to date.
Figure 6. Schematic diagram of a low-sulphidation epithermal deposit
13
newmurchgold.com.a
A wide zone of geochemical anomalism grading from arsenic-rich to antimony-rich with depth at the
Whopper Junior target is highly prospective. Shallow, relatively arsenic-rich rocks with deeper
antimony-rich rocks is a feature observed at the 3.4Moz Pajingo epithermal gold deposit, located in
Queensland. At Pajingo, only anomalous gold is associated with the shallow arsenic-rich zone while
ore-grade gold is associated with antimony and is deeper in the deposit.
Figure 7. September 2025 RC drill collars, main prospects and soil anomaly locations over analytic signal magnetics
demonstrating a broad zone of hydrothermally altered rocks with a low magnetic response.
Airborne Magnetic Surveydata collected in 2025 identified a large zone of demagnetised rocks (see blue
and green colour zones in Figure 7), consistent with magnetite destructive alteration that would be
expected in a large-scale low-sulphidation epithermal system.
14
newmurchgold.com.a
An 820-point 2025 soil sampling campaign resulted in the identification of a number of strong multi-
element soil anomalies bearing key geochemical characteristics of large-scale epithermal gold-silver
systems that are all untested by exploration drilling. Figure 8 and Figure 9 show the location of the
identified anomalies, with gold and antimony geochemistry, respectively.
Figure 8. Gridded gold soil sample geochemistry, major prospects, drill collars and anomaly locations.
15
newmurchgold.com.a
Figure 9. Gridded antimony soil sample geochemistry, major prospects, drill collars and anomaly locations.
Work completed during the quarter
No work was completed during the quarter for the Needles Gold Project.
16
newmurchgold.com.a
Governor Broome Mineral Sands Project, WA
The 100%-owned Governor Broome Mineral Sands Project is located approximately 95km by sealed
road south of Busselton in Western Australia, 105km south of Iluka’s processing plant at Capel, and
135km from Bunbury Port and from Picton, where Doral has a heavy mineral separation plant (Figure
10). A 132kV power line is located just 5km to the north and a three-phase power line passes through
the Governor Broome Project, giving it significant strategic advantages from an infrastructure and
access perspective.
Tenement Category Tonnage (Mt) HM (%) Slimes (%)
R70/58
Jack Track
Measured 20.2 4.2 8.4
Indicated 21 3.5 7.9
Total 41 3.9 8.2
R70/53
Governor Broome
Measured 8.0 5.0 13
Indicated 44 5.0 13
Inferred 7 3.5 12
Total 59 4.8 12.5
R70/22
Fouracres
Indicated 0.72 11.4 6.5
Inferred 0.2 3.5 9
Total 0.93 9.6 7.1
Project
Measured 28.4 4.4 9.7
Indicated 66 4.5 12
Inferred 7 3.5 12
Total 101 4.5 11
Table 6. Governor Broome Project Mineral Resources – at a 2% HM lower block-cut-off grade
Note that the above figures have been appropriately rounded.
The Fouracres Resources estimated at a 3% Heavy Mineral (HM) lower block-cut-off grade
Governor Broome and Jack Track Resources estimated at a 2% HM lower block-cut-off grade
The Company has progressed its de-risking strategy for the Governor Broome Project over the past two
years, with the successful execution of in-fill drilling allowing for the upgrade of Inferred Mineral
Resources to high-value Measured and Indicated status (Table 6), the acquisition of the high-grade
Fouracres deposit, located along strike from Jack Track, and the completion of a bulk test-work
program on samples from the most recent Jack Track drilling campaign.
The bulk test-work program was highly successful, demonstrating the amenability of the Jack Track
Deposit to processing through the feed preparation circuit using conventional mineral sands
processing equipment. The material was processed without difficulty with the sand fraction containing
the valuable heavy minerals (Heavy Mineral Concentrate/HMC) readily liberated from the slimes
without the need for energy intensive processing equipment.
Furthermore, subsequent dry test-work demonstrated that a range of ilmenite, leucoxene, rutile and
zircon products could be recovered from the heavy mineral concentrate.
17
newmurchgold.com.a
Monazite was also recovered to a para-magnetic concentrate stream. Product qualities are consistent
with other heavy mineral products on the market.
Scoping Study
In April 2024, the Company announced the results from the Scoping Study for the Governor Broome
Project and the financial metrics from the Study were exceptionally positive, as tabulated below:
Metric Unit Value
Capital cost A$ million 91
Average annual revenue A$ million 125
Average annual operating cost A$ million 83
Pre-tax NPV (at 10% discount rate) A$ million 139
Pre-tax IRR % 54
Weighted average revenue to cash cost ratio (payback period) - 1.9
Capital Payback Period Years <2
Table 7. Scoping Study material outputs
The full release for the Scoping Study, including detailed assumptions, results and Cautionary
Statements is available in the ASX Announcement dated 4 April 2024.
The Company confirms that all material assumptions underpinning the production targets and
forecast financial information derived from the Scoping Study results in the 4 April 2024 release
continue to apply and have not materially changed.
Figure 10. Governor Broome Project Location, WA.
18
newmurchgold.com.a
Work During the Quarter
No work was undertaken during the quarter on the Governor Broome Project. The Company continues
to actively investigate its options for realising value from the Project, including through potential joint
ventures, an outright trade sale and other avenues.
Georgina Basin IOCG Project, Northern Territory
No activities were undertaken on the Georgina Basin IOCG project.
During the quarter, the Company actively pursued its portfolio simplification strategy to focus on its
Red Mountain Project. On 7 July 2026, the Company entered into a conditional sale of its 100%
shareholding in Knox Resources Pty Ltd (Knox), the owner of the Georgina Basin project and the sale
was completed on the 16 July 2026.
Further details of the sale can be found in the corporate section below.
Corporate
Capital raising
On 20 July 2026, the Company announced that received binding commitments for $6.1 million of
funding, comprising of a two-tranche capital raising totalling $4.750 million plus a convertible note that
is repayable by way of a future share issue totalling $1.350 million. The capital raising was completed
on 31 July 2026.
Sale of Knox
As noted in the activities section above, the Georgina Basin IOCG project was sold shortly after the end
of the quarter. Details of the consideration payable (Sale Price) on completion of the sale of Knox
Resources are provided below:
• Cash - £100,000; and
• Shares in AML - 90,260,854 at a value of £100,000 based on a 5-day volume-weighted average
price of 0.11p. AML has a market capitalisation of approximately £13 million.
The estimated value of the Sale Price is A$386,000.
A further A$277,620 in respect of Research and Development Tax Incentive refunds will be received by
the Company following completion of the sale.
In addition to the above, the Company has into a 12-month services agreement with AML for the
provision of technical services in relation to the Georgina Project. The service fee payable to VMS will
be A$120,000 per annum and additional fees may be payable to VMS where Venari undertakes
significant work in respect of projects unrelated to the Georgina Project.
19
newmurchgold.com.a
ASX Additional Information
The Company provides the following information pursuant to ASX Listing Rule requirements:
1. ASX Listing Rule 5.3.1: Exploration and Evaluation Expenditure spend during the quarter was
$406,801 Full details of exploration activity during the 30 June 2026 quarter are set out in this
report.
2. ASX Listing Rule 5.3.2: The Company confirms that there was no mine production and
development activities for the quarter.
3. ASX Listing Rule 5.3.5: Payment to related parties of the Company and their associates during
the quarter was $202,250 in cash.
The Company advises that this relates to remuneration of Directors only. Set out below is the following
additional information in relation to the cash flow statement:
Name of Director Nature of Payment
Amount ($) [excluding
any GST]
Tony Leibowitz Ongoing Executive Chairman fees 55,000
Matthew Healy
Ongoing Executive Director fees,
including superannuation
82,500
Vincent Fayad
Non-Executive Director, Company
Secretary and Chief Financial Officer
64,750
Table 8. Director’s remuneration
Tenements
In accordance with Listing Rule 5.3.3, Venari provides the following Information concerning its
exploration licences.
• List of Tenement Details
Appendix 1 sets out a list of the Company’s exploration licences held at the end of the quarter.
• Tenements acquired during the quarter and their location
No applications were made during the quarter by the Company to acquire further licences.
• Tenements disposed during the quarter and their location
No tenements were disposed of during the quarter. Subsequent to quarter end, the Company
disposed of its interest in the Georgina Basin tenements (itemised under Appendix 1 as
“Georgina Basin” - refer to the Company's ASX announcement dated 16 July 2026.
• The beneficial percentage interests held in farm-in or farm-out agreements at the end of
the quarter
Nil.
20
newmurchgold.com.a
• The beneficial percentage interests in farm-in or farm-out agreements acquired or
disposed of during the quarter
Nil.
Competent Persons Statements
Nevada Lithium Projects
The information in this report that relates to Nevada Lithium Projects Sampling Techniques and Data
(Section 1) is based on information compiled by Mr Matthew Healy, a Competent Person who is a
Member of The Australasian Institute of Mining and Metallurgy (AusIMM Member number 303597). Mr
Healy is a full-time employee of Venari Minerals NL and is eligible to participate in Share-based
incentive schemes of the Company. Mr Healy has sufficient experience that is relevant to the style of
mineralisation and type of deposit under consideration and to the activity being undertaken to qualify
as a Competent Person as defined in the 2012 Edition of the ‘Australasian Code for Reporting of
Exploration Results, Mineral Resources and Ore Reserves’. Mr Healy consents to the inclusion in the
report of the matters based on his information in the form and context in which it appears.
The information in this report that relates to the Nevada Lithium Projects Reporting of Exploration
Results (Section 2) and Mineral Resource Estimates is based on information compiled by Mr Richard
Newport, principal partner of Richard Newport & Associates – Consultant Geoscientists. Mr Newport
is a member of the Australian Institute of Geoscientists and has sufficient experience which is relevant
to the style of mineralisation and type of deposit under consideration and to the activity which he is
undertaking to qualify as a Competent Person under the 2012 Edition of the ’Australasian Code for
Reporting of Exploration Results, Mineral Resources and Ore Reserves‘. Mr. Newport consents to the
inclusion in thisannouncementof thematters based onhis information in theform and context in which
it appears.
Georgina Basin
The information in this report that relates to Exploration Results associated with the NT Georgina
project is based on information compiled by Mr Matthew Healy, a Competent Person who is a Member
of The Australasian Institute of Mining and Metallurgy (AusIMM Member number 303597). Mr Healy is a
full-timeemployee of Venari Minerals NL and is eligibleto participate in share-based incentive schemes
of the Company. Mr Healy has sufficient experience that is relevant to the style of mineralisation and
type of deposit under consideration and to the activity being undertaken to qualify as a Competent
Person as defined in the 2012 Edition of the ‘Australasian Code for Reporting of Exploration Results,
Mineral Resources and Ore Reserves’. Mr Healy consents to the inclusion in the report of the matters
based on his information in the form and context in which it appears.
Governor Broome
The information in this report as it relates to MineralResources and Exploration Resultsfor the Governor
Broome Project is based on information compiled by John Doepel, a Director of Continental Resource
Management Pty Ltd (CRM), who is a member of the Australasian Institute of Mining and Metallurgy. Mr
Doepel has sufficient experience in mineral resource estimation relevant to the style of mineralisation
and type of deposit under consideration to qualify as
Share your feedback
Discover