POSITIVE INITIAL METALLURGICAL RESULTS FROM RED
MOUNTAIN LITHIUM PROJECT, USA
Strong lithium leachability results enhance project potential
Key Highlights
•
Initial leachability and mineralogy test-work completed for
six RC samples from drill-holes completed across the Red
Mountain Project area.
•
High lithium leachability results returned, including:
•
94-98% lithium leached in acid concentration tests
•
82-97% lithium leached in heated tests at 60°C
•
94-98% lithium leached in leach time tests within 24hrs
and 70-97% leached within 4hrs
•
Leaching test-work shows that lithium is readily leachable
from the Red Mountain host rocks.
•
Increasing lithium grades observed with increasing clay
content.
•
Assay results from the October diamond drilling program
expected in the coming weeks.
Astute Metals NL (ASX: ASE) (“ASE”, “Astute” or “the Company”) is pleased to report results from the initial
metallurgical test-work completed at its 100%-owned Red Mountain Lithium Project in Nevada, USA. The
early-stage test-work was primarily designed to test for lithium leachability, how leachability changes
with temperature, acid concentration and time, and to evaluate bulk sample mineralogy.
The test-work program, which was conducted on samples from the Company’s maiden RC drilling
campaign, was highly successful, indicating lithium leachability of up to 98% - results that are
comparable to or better than announced leachability results for other projects7. Background to the Red
Mountain Project is on page seven of this ASX Release.
Processing of lithium clays comprise three generalised stages: leaching of lithium from the clays into a
pregnant leach solution (PLS); removal of impurities from the PLS; and crystallization of a final lithium
product. These initial results are an important step in demonstrating the ability for lithium to be liberated
from the clays at Red Mountain. The results will guide future metallurgical work which will aim to optimise
leach conditions, test the ability to beneficiate or ‘upgrade’ mineralised material, and ultimately produce
a final lithium product such as lithium carbonate.
Astute Chairman, Tony Leibowitz, said:
“This is another very encouraging step in our journey to unlock the potential of the Red Mountain
clay-hosted lithium discovery. Achieving high leachability results of up to 98% is a great outcome
which shows that we can successfully liberate lithium from the clays into a pregnant leach solution.
While further work is required to optimize the leach conditions and the other steps in the process
towards producing a battery-grade lithium product, this is a very important piece of baseline work
that sets a strong foundation for us moving forward. We are now looking forward to receiving
assays results from our recent diamond drilling program as the next key catalyst for the Red
Mountain Project.”
Suite 6, Level 5, 189 Kent St, Sydney NSW 2000 | GPO Box 2733, Sydney NSW 2001
+61 (0) 2 8046 2799 | admin@astutemetals.com
www.astutemetals.com
Figure 1. Red Mountain metallurgical samples at Kappes Cassiday & Associates lab in Reno, Nevada.
Test-work Overview
In September 2024, the Company despatched six samples from its June 2024 RC drilling campaign to
metallurgy group Kappes, Cassiday & Associates (KCA) for scoping-level lithium leach test-work
(Figure 1). KCA, which is based in Reno, approximately 500km west of the Red Mountain Project, is highly
regarded for its leach test-work expertise in lithium, copper and gold.
The test-work included head sample analyses, acid concentration leaching, leach time testing, leach
temperature testing and associated tails and solution assays. In addition, a sub sample of each of the
six RC samples submitted was sent to FLSmidth for bulk mineral identification using
Quantitative X-Ray Diffraction (QXRD) and Cation Exchange Capacity (CEC) methods.
The purpose of the test-work was to confirm that lithium can be leached from mineralised rock types
at Red Mountain, to establish scoping-level rates of leachability and acid consumption, and to guide
future metallurgical work. Results tables for metallurgical testwork, including head assays, solution and
tails assays, for each test is shown in Appendix 2.
Metallurgical Sample Selection
For the scoping level test-work, six samples were selected from drill-holes located in the north, central
and south parts of the Red Mountain Project (Figure 2).
Samples were selected to cover a range of lithium grades, depths, lithologies and other characteristics,
in order to gain an understanding of the variability in high-level leachability characteristics across the
Project. A summary of the metallurgical samples is provided below:
Sample ID
Sample Type
Hole ID
Interval (ft)
Lithology
100756 A
RC Chips
RMRC001
255 - 260
Silty Claystone
100757 A
RC Chips
RMRC001
295 - 300
Silty Claystone
100758 A
RC Chips
RMRC002
5 - 10
Claystone
100759 A
RC Chips
RMRC003
70 - 75
Limestone
100760 A
RC Chips
RMRC005
255 - 260
Siltstone
100761 A
RC Chips
RMRC005
330 - 335
Clayey Siltstone
Table 1. Metallurgical sample details
Suite 6, Level 5, 189 Kent St, Sydney NSW 2000 | GPO Box 2733, Sydney NSW 2001
+61 (0) 2 8046 2799 | admin@astutemetals.com
www.astutemetals.com
Figure 2. Metallurgical sample location plan.
Easting
Northing
RL
Dip
Azimuth
Depth Drilled
(NAD83)
(NAD83)
(m)
(°)
(°)
(m)
RMRC001
637610
4285589
1708
-50
180
182.9
RMRC002
637105
4290201
1694
-50
270
128.0
RMRC003
637105
4290201
1694
-90
-
36.6
RMRC005
637321
4288194
1687
-50
270
137.2
Drill Hole ID
Table 2. Drill-hole collar details from which metallurgical samples were selected
Lithium leachability by acid concentration
Leachability by acid concentration tests were conducted using pulverized sample at a target pulp
density of 10% solids by weight. Three tests were conducted with varying acid concentration (219 –
902kg/t) at an ambient 21°C temperature to determine the influence on overall lithium extraction and
acid consumption. Results are plotted in Figure 3.
The acid concentration tests showed high lithium extractions of 94-98% in a 24-hour leach with nominal
900kg/t acid addition, with acid consumptions ranging from 406 – 529kg/t.
Lithium leachability was lower with lower acid additions of 220 and 450kg/t.
Suite 6, Level 5, 189 Kent St, Sydney NSW 2000 | GPO Box 2733, Sydney NSW 2001
+61 (0) 2 8046 2799 | admin@astutemetals.com
www.astutemetals.com
100%
90%
80%
Li Extraction
70%
60%
50%
40%
30%
20%
10%
0%
0
100
200
300
400
500
600
700
800
900
1,000
Sulfuric Acid Addition, kg/MT
100756 A
100757 A
100758 A
100759 A
100760 A
100761 A
Figure 3. Lithium leachability by acid concentration.
Lithium leachability by time
Leachability by time tests were conducted using pulverized sample at a target pulp density of 10% solids
by weight. Four tests were conducted (887 - 902kg/t sulfuric acid addition at an ambient 21°C
temperature) with leaching timeframes of 1, 2, 4 and 24 hours to determine the influence of time on
lithium extraction. Results are plotted in Figure 4.
Leach time tests demonstrated high lithium extractions of 91-97% in a 4-hour leach for four of the six
samples, with the remaining two showing extractions of 70% and 72% for this timeframe. Acid
consumptions ranged 375-475kg/t in the 4-hour tests.
At a 24-hour leach, extractions were all high at between 94% and 98%, with acid consumptions of 406529kg/t.
100%
90%
80%
Li Extraction
70%
60%
50%
40%
30%
20%
10%
0%
0
5
10
15
20
25
30
Leach Time, hours
100756 A
100757 A
100758 A
100759 A
100760 A
Figure 4. Lithium leachability by time.
Suite 6, Level 5, 189 Kent St, Sydney NSW 2000 | GPO Box 2733, Sydney NSW 2001
+61 (0) 2 8046 2799 | admin@astutemetals.com
www.astutemetals.com
100761 A
Lithium leachability by temperature
Leachability by temperature tests were conducted using pulverized sample at a target pulp density of
10% solids by weight. Two tests were conducted (887-912 kg/t sulfuric acid addition) at 21°C and 60°C
temperatures to determine the influence of temperature on lithium extraction.
The tests demonstrated that leach kinetics improved with heat, with 21-92% lithium leachability at
ambient temperature, increasing substantially to 82-97% at a temperature of 60°C (Figure 5).
100%
21°C
90%
60°C
80%
Li Extraction
70%
60%
50%
40%
30%
20%
10%
0%
100756 A
100757 A
100758 A
100759 A
100760 A
100761 A
Met Sample ID
Figure 5. Lithium leachability by temperature.
Mineralogy
The clay content of the samples ranged from 16.8 – 35.9% based on cation exchange capacity (CEC)
analysis, demonstrating a positive relationship with lithium grades (Figure 6). Other major minerals
making up the samples include K-feldspar (16.8 – 34%), calcite (17.4 – 29.4%) and plagioclase (5 –
7.7%). Trace amounts of anhydrite in some samples is interpreted to indicate the evaporative nature of
the closed basin in which the sedimentary package was deposited. A full table of QXRD and CEC results
is shown in Appendix 3.
Average Head Grade (ppm Li)
3,000
y = 52.578x + 276.8
2,500
R² = 0.6441
2,000
1,500
1,000
500
0
0
5
10
15
20
25
30
35
Swelling Clay (CEC, wt%)
Figure 6. Clay content and average head grades for metallurgical samples.
Suite 6, Level 5, 189 Kent St, Sydney NSW 2000 | GPO Box 2733, Sydney NSW 2001
+61 (0) 2 8046 2799 | admin@astutemetals.com
www.astutemetals.com
40
Interpretation
The results of this scoping-level testwork are highly encouraging for the Red Mountain Project,
particularly at this early stage. The main conclusions drawn from the testwork are:
•
•
•
•
Sulfuric-acid leaching shows that lithium is readily leachable from the clay-bearing host rocks
at Red Mountain.
High recoveries of up to 98% of lithium are achievable using appropriate conditions.
The overall recovery of lithium is a function of temperature, acid strength and time conditions.
Lithium grade in samples increases with clay content, indicating that focusing future exploration
work on project areas with higher clay content may result in intersection of higher lithium grades.
The Red Mountain results compare favourably with other lithium clay project leachability results, such
as those for Surge Battery Metals’ (TSX: NILI) Nevada North project, which had lower lithium leachability
extraction (%) in acid concentration tests7.
Next Steps
Future metallurgical work for Red Mountain will include assessment for beneficiation potential,
optimisation of leach conditions in terms of acid concentration, time and temperature, and assessment
of leaching with other acids (e.g. hydrochloric acid). Beneficiation testwork is of particular interest, as
this would aim to separate and remove acid-consuming minerals, such as calcite, from the lithiumbearing clay minerals. If successful, beneficiation may result in reduced acid consumption, reduced
mass, and increased lithium grade.
The Company is expecting assay results for the two October 2024 diamond drill-holes completed at
Red Mountain in the coming weeks. Subject to the results received, the remaining drill core is available
for use in future metallurgical test-work aimed at de-risking processing characteristics of the Project.
Figure 7. Location of Astute Lithium Projects and Nevada lithium deposits.
Suite 6, Level 5, 189 Kent St, Sydney NSW 2000 | GPO Box 2733, Sydney NSW 2001
+61 (0) 2 8046 2799 | admin@astutemetals.com
www.astutemetals.com
Background
Located immediately adjacent to Route 6 near the township of Currant in central-eastern Nevada, the
Red Mountain Project was staked in August 2023. The Project area has broad mapped tertiary lacustrine
(lake) sedimentary rocks known locally as the Horse Camp Formation.
Elsewhere in the State of Nevada, equivalent rocks host large lithium deposits (see Figure 7) such as
Lithium Americas’ (NYSE: LAC) 16.1Mt LCE Thacker Pass Project 2, the American Battery Technology
Corporation’s (OTCMKTS: ABML) 16.9Mt LCE Tonopah Flats deposit 3 and the American Lithium (TSX.V: LI)
10.7Mt LCE TLC Lithium Project4.
Astute has completed substantial surface sampling campaigns at Red Mountain, which indicate
widespread lithium anomalism in soils and confirmed lithium mineralisation in bedrock with some
exceptional grades of up to 4,150ppm Li1,6.
The Company’s maiden drill campaign at Red Mountain comprised 11 RC drill holes for 1,518m over a
4.6km strike length. This campaign was highly successful with strong lithium mineralisation intersected
in every hole drilled5. Two diamond drill holes have been drilled at the project for which assays are
pending8.
Other attractive Project characteristics include close proximity to infrastructure, with the Project being
immediately adjacent to the Grand Army of the Republic Highway (Route 6), which links the regional
cities of Ely with Tonopah.
1 ASX: ASE 8 July 2024 ‘High-Grade Rock Chip Assays at Red Mountain Project’
2 NYSE: LAC 2 November 2022 Feasibility Study NI 43-101 Technical Report for the Thacker Pass Project
3 NASDAQ: ABAT Updated Resource Estimate and Initial Assessment… 21 December 2023..’
4 TSX.V: LI 17 March 2023 ‘Tonopah Lithium Claims project NI 43-101 technical report – Preliminary Economic Assessment’
5 ASX: ASE 7 August 2024 ‘Receipt of Final Assays for the Red Mountain Project’
6 ASX: ASE 20 November 2023 ‘Large Lithium Soil Anomalies Discovered at Red Mountain’
7 TSX: NILI April 5 2023 Surge Battery Metals Nevada North Lithium Project NI 43-101 Report
8 ASX: ASE 10 October 2024 ‘Diamond drilling Commences at the Red Mountain Lithium Project’
Authorisation
This announcement has been authorised for release by the Board of Astute.
More Information
Matt Healy
Executive Director & CEO
mhealy@astutemetals.com
+61 (0) 431 683 952
Nicholas Read
Media & Investor Relations
nicholas@readcorporate.com.au
+61 (0) 419 929 046
Competent Persons
The information in this report that relates to Sampling Techniques and Data (Section 1) is based on
information compiled by Mr. Matthew Healy, a Competent Person who is a Member of The Australasian
Institute of Mining and Metallurgy (AusIMM Member number 303597). Mr. Healy is a full-time employee
of Astute Metals NL and is eligible to participate in a Loan Funded Share incentive plan of the Company.
Mr. Healy has sufficient experience that is relevant to the style of mineralisation and type of deposit
under consideration and to the activity being undertaken to qualify as a Competent Person as defined
in the 2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources and
Ore Reserves’. Mr. Healy consents to the inclusion in the report of the matters based on his information
in the form and context in which it appears.
The information in this report that relates to Reporting of Exploration Results (Section 2) is based on
information compiled by Mr. Richard Newport, principal partner of Richard Newport & Associates –
Consultant Geoscientists. Mr. Newport is a member of the Australian Institute of Geoscientists and has
sufficient experience which is relevant to the style of mineralisation and type of deposit under
consideration and to the activity which he is undertaking to qualify as a Competent Person under the
2012 Edition of the ’Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore
Reserves‘. Mr. Newport consents to the inclusion in this announcement of the matters based on his
information in the form and context in which it appears.
Suite 6, Level 5, 189 Kent St, Sydney NSW 2000 | GPO Box 2733, Sydney NSW 2001
+61 (0) 2 8046 2799 | admin@astutemetals.com
www.astutemetals.com
APPENDIX 1 - JORC Code, 2012 Edition – Table 1
Section 1 - Sampling Techniques and Data
Criteria
JORC Code explanation
Commentary
Sampling
techniques
Nature and quality of sampling (e.g. cut
channels, random chips, or specific
specialisedindustry standard measurement
tools appropriate to the minerals under
investigation, such as down hole gamma
sondes, or handheldXRF instruments, etc.).
These examples should not be taken as
limiting the broad meaning of sampling.
5.5” reverse circulation drilling was undertaken for
drill sample collection. Samples were collected on
a 5-foot basis in calico bags, with a 50% split
retained from a rotary cone splitter for initial lab
assay.
Include reference to measures taken to
ensuresample representivity and the
appropriate calibration of any measurement
tools or systems used.
Aspects of the determination of mineralisation
thatare Material to the Public Report.
In cases where ‘industry standard’ work has
been done this would be relatively simple
(e.g. ‘reverse circulation drilling was used to
obtain 1 m samples from which 3 kg was
pulverised to produce a 30 g charge for fire
assay’). In other cases, more explanation may
be required, suchas where there is coarse
gold that has inherentsampling problems.
Unusual commodities or mineralisation types
(e.g. submarine nodules) may warrant
disclosure of detailed information.
The remaining 50% was retained, and formed the
basis for sample material for metallurgical
testwork as discussed in this release.
Samples were air dried on elevated grid meshuntil
practical to transport
Claystone hosted lithium deposits are thought to
form as a result of the weathering of
lithium-bearing volcanic glass within
tertiary-aged tuffaceous lacustrine sediments of
the mapped Ts3 unit. Inputs of lithium from
geothermal sources have also been proposed.
Drilling
techniques
Drill type (e.g. core, reverse circulation, openholehammer, rotary air blast, auger, Bangka,
sonic, etc.) and details (e.g. core diameter,
triple or standard tube, depth of diamond tails,
face-sampling bit or other type, whether core
isoriented and if so, by what method, etc.).
5.5” reverse circulation drilling methods employed.
Water was injected to assist with transport of
sample from bit to surface, as required.
Drill sample
recovery
Method of recording and assessing core and
chip sample recoveries and results assessed.
Sample recovery established by dry sample
weights undertaken by independent laboratory
prior to sample preparation and analysis
Measures taken to maximise sample recovery
and ensure representative nature of the
samples.
Whether a relationship exists between
sample recovery and grade and whether
sample bias may have occurred due to
preferential loss/gainof fine/coarse material.
Logging
Whether core and chip samples have been
geologically and geotechnically logged to a
level of detail to support appropriate Mineral
Resource estimation, mining studies and
metallurgical studies.
Whether logging is qualitative or quantitative
innature. Core (or costean, channel, etc.)
photography.
The total length and percentage of the
relevantintersections logged.
Some instances of poor recovery near surface.
Instances of poor recovery are not expected to
materially impact interpretation of results
KCA undertook sample weights on receipt
Drill cuttings for entire hole logged for lithology by
company geologists
Logging is qualitative
Photography of material intersections ofclaystone
taken of relevant chip trays
Photography of metallurgical samples
undertaken by KCA on receipt
Suite 6, Level 5, 189 Kent St, Sydney NSW 2000 | GPO Box 2733, Sydney NSW 2001
+61 (0) 2 8046 2799 | admin@astutemetals.com
www.astutemetals.com
APPENDIX 1 - JORC Code, 2012 Edition – Table 1
Criteria
JORC Code explanation
Commentary
Subsampling
techniques
and sample
preparation
If core, whether cut or sawn and whether
quarter, half or all core taken.
Samples, once received by KCA, were crushed to
100% passing 6.3mm to break up lumps within
the sample. A 1,500g sub-sample was split out
for testwork as described in this announcement.
If non-core, whether riffled, tube sampled, rotary
split, etc. and whether sampled wet or dry.
For all sample types, the nature, quality and
appropriateness of the sample preparation
technique.
Quality control procedures adopted for all
sub-sampling stages to maximise
representivityof samples.
The 1,500g portions were air-dried overnight and
re-weighed. Dried material was pulverized to
100% passing 0.106mm. This pulverized material
were split to yield portions for head assays and
acid leach testing, with a separate sample split
out for XRD and CEC analysis at FL Smidth
Measures taken to ensure that the sampling is
representative of the in-situ material
collected,including for instance results for field
duplicate/second-half sampling.
Quality of
assay data
and
laboratory
tests
Whether sample sizes are appropriate to the
grain size of the material being sampled.
The nature, quality and appropriateness of the
assaying and laboratory procedures used and
whether the technique is considered partial or
total.
For geophysical tools, spectrometers, handheld
XRF instruments, etc., the parameters used in
determining the analysis including instrument
make and model, reading times, calibrations
factors applied and their derivation, etc.
Nature of quality control procedures adopted
(e.g. standards, blanks, duplicates, external
laboratory checks) and whether acceptable
levels of accuracy (i.e. lack of bias) and
precisionhave been established.
Verification
of sampling
and
assaying
The verification of significant intersections by
either independent or alternative company
personnel.
The use of twinned holes.
Head analyses were performed using a 4-acid
digest and ICP-OES for individual elements.
Free acid was determined through titration to pH 3
of a solution sample, in a methanol solution using
sodium hydroxide. The methanol solution contained
0.5 molar Me-MgCl2 to reduce the effects of
hydrolysable cations such as Fe3+, Al3+ and Cu2+.
The pH endpoint was measured using a calibrated
pH meter.
Acid consumption was calculated as the difference
between the acid added and the free acid
measured in the final pregnant leach solution plus
wash.
Reagent grade concentrated acid was utilized for
leach tests. The effective concentration of the acid
was measured using titration as per above.
Sample, when received by KCA, were assigned a
unique KCA sample identification number that
was recorded against the sample ID provided by
Astute Metals.
Documentation of primary data, data entry
procedures, data verification, data storage
(physical and electronic) protocols.
Discuss any adjustment to assay data.
Location of
data points
Accuracy and quality of surveys used to locate
drill holes (collar and down-hole surveys),
trenches, mine workings and other locations
used in Mineral Resource estimation.
Specification of the grid system used.
Quality and adequacy of topographic control.
Drill collar locations determined using hand-held
GPS with location reported in NAD83 UTM Zone 11.
Expected hole location accuracy of +/- 10m
No downhole surveys conducted on drill holes,
with drill rigs lined up by compass and clino at
start of hole
Suite 6, Level 5, 189 Kent St, Sydney NSW 2000 | GPO Box 2733, Sydney NSW 2001
+61 (0) 2 8046 2799 | admin@astutemetals.com
www.astutemetals.com
APPENDIX 1 - JORC Code, 2012 Edition – Table 1
Criteria
JORC Code explanation
Commentary
Data spacing
anddistribution
Data spacing for reporting of Exploration
Drill spacing is appropriate for early exploration
purposes
Results.
Whether the data spacing and distribution
is sufficient to establish the degree of
geological and grade continuity appropriate
for the MineralResource and Ore Reserve
estimation procedure(s) and
classifications applied.
5-foot sample interval widely adopted as
standard practice in air drilling in the USA.
Whether sample compositing has been
applied.
Orientationof
data in relation
to geological
structure
Whether the orientation of sampling
achieves unbiased sampling of possible
structures and the extent to which this is
known, considering thedeposit type.
Claystone beds are regionally shallow-dipping at
~20° to the east although locally this may vary
across the Project with some evidence of faulting
and potential folding
If the relationship between the drilling
orientation and the orientation of key
mineralised structures is considered to have
introduced a sampling bias, this should be
assessed and reported if material.
Samplesecurity
The measures taken to ensure sample
security.
Samples stored at secured yard and shed located
in township of Currant until freighted by UPS to the
KCA lab at Reno, NV
Audits orreviews
The results of any audits or reviews of
samplingtechniques and data.
Not applicable
Suite 6, Level 5, 189 Kent St, Sydney NSW 2000 | GPO Box 2733, Sydney NSW 2001
+61 (0) 2 8046 2799 | admin@astutemetals.com
www.astutemetals.com
APPENDIX 1 - JORC Code, 2012 Edition – Table 1
Section 2 - Reporting of Exploration Results
Criteria
JORC Code explanation
Commentary
Mineral
tenement
and land
tenure status
Type, reference name/number, location and
ownership including agreements or material
issues with third parties such as joint ventures,
partnerships, overriding royalties, native title
interests, historical sites, wilderness or nationalpark
and environmental settings.
Red Mountain Claims held in 100% Astute
subsidiary Needles Holdings Inc.
The security of the tenure held at the time of
reporting along with any known impediments to
obtaining a licence to operate in the area.
Exploration
done by
other parties
Acknowledgment and appraisal of exploration by
other parties.
Geology
Deposit type, geological setting and style of
mineralisation.
Claims located on Federal (BLM) Land
Drilling conducted on claims certified by the
Bureau of Land Management (BLM)
No known previous lithium exploration conducted
at Red Mountain
Exploration conducted elsewhere in Nevada by
other explorers referenced in announcement
body text
The principal target deposit style is claystone
hosted lithium mineralisation. Claystone hosted
lithium deposits are thought to form as a result of
the weathering of lithium-bearing volcanic glass
within tertiary-aged tuffaceous lacustrine
sediments of the mapped Ts3 unit.
Lacustrine environments formed as a result of
extensional tectonic regime that produced ‘basin
and range’ topography observed across the
stateof Nevada. Inputs of lithium from
geothermal sources have also been proposed.
Drill hole
Information
A summary of all information material to the
understanding of the exploration results including
a tabulation of the following information for all
Material drill holes:
◦ easting and northing of the drill hole collar
◦ elevation or RL (Reduced Level – elevation
above sea level in metres) of the drill hole
collar
◦ dip and azimuth of the hole
◦ down hole length and interception depth
◦ hole length.
Drillhole locations, orientations and drilled depths
are tabulated in body report
If the exclusion of this information is justified on the
basis that the information is not Material and this
exclusion does not detract from the
understanding of the report, the Competent
Person should clearly explain why this is the case.
Data
aggregation
methods
In reporting Exploration Results, weighting
averaging techniques, maximum and/or
minimum grade truncations (e.g. cutting of high
grades) and cut-off grades are usually Material
and should be stated.
Where aggregate intercepts incorporate short
lengths of high grade results and longer lengths of
low grade results, the procedure used for such
aggregation should be stated and some typical
examples of such aggregations should be shown
in detail.
The assumptions used for any reporting of metal
equivalent values should be clearly stated.
Intersections, where quoted are weighted by
length. Lengths originally recorded in feet are
quoted to the nearest 10cm.
Rounding is conducted to 3 significant figures
A 500ppm Li cut-off was used to quote
headline intersections, with allowance for 5ft of
internal dilution by lower grade material.
Low grade mineralisation (300-500ppm Li) is
present outside of the quoted intersections
Intersections are quoted in both lithium ppm and
as wt% Lithium Carbonate Equivalent (LCE). LCE is
calculated as LCE = Li (ppm) x 5.323 / 10,000, as
per industry conventions.
Suite 6, Level 5, 189 Kent St, Sydney NSW 2000 | GPO Box 2733, Sydney NSW 2001
+61 (0) 2 8046 2799 | admin@astutemetals.com
www.astutemetals.com
Section 2 Reporting of Exploration Results
Criteria
JORC Code explanation
Commentary
Relationship
between
mineralisatio
n widths and
intercept
lengths
These relationships are particularly important in
the reporting of Exploration Results.
Insufficient information available due to early
exploration status
If the geometry of the mineralisation with respect
to the drill hole angle is known, its nature should be
reported.
If it is not known and only the down hole lengths
are reported, there should be a clear statement
to this effect (e.g. ‘down hole length, true width not
known’).
Diagrams
Appropriate maps and sections (with scales)
andtabulations of intercepts should be included
for any significant discovery being reported
These should include, but not be limited to a plan
view of drill hole collar locations and appropriate
sectional views.
Included in ASX announcement
Balanced
reporting
Where comprehensive reporting of all Exploration
Results is not practicable, representative
reporting of both low and high grades and/or
widths should be practiced to avoid misleading
reporting of Exploration Results.
This release describes all relevant information
Other
substantive
exploration
data
Other exploration data, if meaningful and material,
should be reported including (but not limited to):
geological observations; geophysicalsurvey
results; geochemical survey results; bulk samples
– size and method of treatment; metallurgical
test results; bulk density, groundwater,
geotechnical and rock characteristics; potential
deleterious or contaminating substances.
This release describes all relevant
Share your feedback
Discover