Venari Advances By-Product Strategy at Red Mountain Project
Released
Released
Announcement PDF
ASX / Media Release
1 July 2026
Suite 114-115 Level 1, 165 Phillip St Sydney, NSW 2000
GPO Box 2733, Sydney NSW 2001
P. +61 (0) 2 8046 2799 | E. admin@venariminerals.com
venariminerals.com
Venari Advances Strategy to Unlock Additional Value from Red
Mountain Lithium Project By-Products
Systematic approach to expand value beyond lithium from significant by-product potential
Highlights
• Recent metallurgical test-work has identified the potential to recover strontium and
magnesium alongside lithium carbonate at the Red Mountain Project in Nevada, USA.
• Potential by-product recovery could:
o Diversify future project revenues;
o Improve resource utilisation;
o Enhance project economics;
o Strengthen Red Mountain’s alignment with US critical and strategic mineral priorities.
• Strontium has been declared a Strategic Material by the US Department of War due to its
pyrotechnic utility in tracer ordnance and flares. The US is 100% import-dependent on supply.
• Magnesium is a US Department of Energy Critical Mineral with a rapidly growing global
market. The US is 59% import-dependent for the magnesium compound Epsomite.
• Venari’s systematic strategy to create value from by-products includes:
o Metallurgical testing to extract by-products from leachate and/or residues;
o Addition of strontium and magnesium to the Red Mountain Mineral Resource Estimate;
o Seeking strategic partnerships to maximise by-product value;
o Seek US Government support programs for critical and strategical minerals such as
grant funding and fast-tracked permitting.
• Updated Inferred Mineral Resource Estimate expected in Q3 2026 to include strontium and
magnesium.
• Scoping Study incorporating by-product options targeted for completion in Q1 2027 for the
Red Mountain Lithium Project22
.
Venari Chief Executive Officer, Matthew Healy, said: “Red Mountain has always been viewed as a
highly prospective lithium project, but recent metallurgical work suggests there may be an opportunity
to unlock significant additional value through the recovery of strategic by-products.
“Our immediate priority is to determine whether strontium and magnesium can be recovered
economically alongside lithium production.”
Venari Chairman, Tony Leibowitz, said: "If successful, these high-value by-products have the
potential to further enhance project economics, diversify future revenue streams and further strengthen
Red Mountain’s strategic importance within US critical mineral supply chains.
2
newmurchgold.com.a
“Importantly, this isn’t about changing the focus of the project – rather it’s about maximising value from
the existing resource through a disciplined and systematic technical evaluation.
“Over the next 12 months we’ll advance metallurgical testing, update the Mineral Resource Estimate to
include these commodities and incorporate by-product opportunities into the Scoping Study, giving
investors a much clearer understanding of the project’s overall value proposition.”
Overview
Venari Minerals NL (ASX: VMS) (“VMS”, “Venari” or “the Company”) is pleased to outline its strategy
to evaluate and potentially commercialise strontium and magnesium by-products from its 100%-
owned Red Mountain Lithium Project in Nevada, USA.
Recent metallurgical test work, undertaken as part of the Company’s lithium process development
program, identified the presence of magnesium and strontium within the sulfuric acid leach circuit,
alongside the production of battery-grade lithium carbonate.
While further metallurgical and economic evaluation is required, these minerals have the potential to
provide additional revenue streams, improve overall resource utilisation and reduce waste, improve
ESG credentials, and further strengthen the strategic positioning of the Red Mountain Project within the
US critical minerals supply chain – particularly for defence-critical strontium.
The Company has commenced a structured program to assess the commercial potential of these by-
products through additional metallurgical testing, incorporation into the next Mineral Resource
Estimate update and evaluation within the planned Scoping Study22
.
Strontium – a strategic defence material
While not currently listed as a critical mineral in the US, strontium is used in defence applications such
as tracers in ordnance, flares, as well as in other pyrotechnics, alloys, ceramics, glasses and nuclear
batteries. Accordingly, Strontium is listed as a strategic material on the Defense Logistics Agency, or
DLA (the US’ logistics combat support agency of the Department of War) Strategic Materials of Interest
list, which can be viewed here: https://www.dla.mil/Strategic-Materials/Materials/#metal.
The global strontium market volumes are on the order of several hundred thousand tonnes per year
(various estimates place global demand in the 300–600kt range depending on scope and year), and US
demand typically runs into the tens of thousands of tonnes range when including processed forms12
.
Strontium carbonate, the common processed form of Strontium, typically commands a price of
US$2,000 per tonne landed in the US, however higher purity products can sell for over $14,000/t20
.
The United States is 100% net import reliant for strontium18
, and the National Defense Authorisation
Act 2023 mandates domestic US (or select ally country) sourcing of defence-related chemicals,
including strontium compounds, by 2028, creating an incentive to establish domestic sources of
strontium to feed into critical defence supply chains. This in turn creates the potential for premium
offtake rates, government support, and/or defence contractor partnerships. The incentive to establish
domestic supply in the US is compounded by supply concentration risks with major producers
including China, Mexico, Spain and Iran.
3
newmurchgold.com.a
This creates a compelling strategic opportunity for Venari. The potential to establish domestic US
production from a Nevada lithium operation offers clear logistical and geopolitical advantages.
Magnesium – a US Critical Mineral
Magnesium is listedon the currentUS Departmentof EnergyCritical Minerals list.Magnesium hasmany
uses: in the metal form, it is used to reduce weight in vehicles and as the hydrated sulfate compound –
Epsomite – has diversified uses including in fertilizers, pharmaceuticals and industrial water treatment
as a flocculant.
The magnesium sulfate market is 2.7 million tonnes annually, of which the North American share is
estimated at 25%, and is expected to grow to 3.7Mt by 203421
. The US currently imports 59% of its
magnesium sulfate, mainly from China18
.
Epsomite prices in the US have ranged from US $370-430/t in the past year11
, indicating a compelling
incentive for the Company to further investigate this potentially valuable by-product, particularly when
the production of lithium carbonate already necessitates magnesium removal.
Creating Value
The integration of by-product streams into Venari’s development strategy for Red Mountain Lithium
Project offers multiple opportunities to extract value:
Revenue Diversification and Economics: By-products have the potential to contribute meaningfully to
future project cash flows, reducing the effective cost of lithium production and improving overall
returns.
Strategic and Geopolitical Positioning: Strontium production directly addresses US strategic mineral
vulnerabilities and defence supply chain mandates.This has the potential to attract offtake agreements
with US government entities and defence contractors, as well as adding potential eligibility for grants,
tax incentives, or fast-tracked permitting under critical minerals policies.
Operational Synergies: By-product recovery reduces waste volumes sent to tailings, improves resource
utilisation and strengthens the project’s sustainability profile.
Processing Integration: Lithium leach circuits (acid-based or otherwise) can generate magnesium- and
strontium-bearing solutions or residues. Targeted separation (e.g., precipitation, crystallisation) can be
engineered into the flowsheet with relatively incremental capital, leveraging existing infrastructure.
Risk Mitigation: Commodity price and market risk is spread across lithium (battery/EV focus) and other
industrial/strategic minerals.
A systematic approach
The Company will systematically evaluate and advance the by-product potential of Red Mountain:
1. Metallurgical test-work (2026): Conduct dedicated testwork to quantify recoverable
grades/yields of strontium and magnesium compounds, with a focus on achieving commercial-
4
newmurchgold.com.a
grade specifications (e.g., purity for defence, agricultural use). Test-work will consider
extracting by-products in potentially various forms from leachate/residue according to whether
lithium is extracted by sulfuric acid, hydrochloric acid, etc. Other potential by-products may be
identified as a result of test-work.
2. Addition to Mineral Resource Estimates (2026): Incorporate strontium and magnesium into the
current Inferred category MRE to define potential by-product tonnages and grades.
3. Funding and Partnerships: Explore strategic partnerships or offtake-linked financing. Seek US
government support programs targeting critical minerals and domestic processing (ongoing).
4. Economic Studies: Include by-product scenarios in Scoping Study (Q1 2027)22
.
Summary
The identification of strontium and epsomite by-products at Red Mountain significantly enhances the
project’s attractiveness. Strontium offers high strategic upside aligned with US national security
priorities, while magnesium sulfate provides stable, diversified industrial demand. Together, they
support a more robust, lower-risk, and higher-value development pathway.
Background
The Red Mountain Project area has broad mapped tertiary lacustrine (lake) sedimentary rocks known
locally as the Horse Camp Formation. Elsewhere in Nevada, equivalent rocks host large lithium
deposits (see Figure 3) such as Lithium Americas’ (NYSE: LAC) 62.1Mt LCE10
Thacker Pass Project3
and
American Battery Technology Corporation’s (NASDAQ: ABAT) 18.7Mt LCE Tonopah Flats deposit4
.
A total of 32 drill holes have been completed at the project to date for a combined 6,015m of drilling
across four campaigns (Figure 1). These campaigns have been highly successful, intersecting strong
lithium mineralisation in almost every hole6,9
.
The Red Mountain maiden Mineral Resource Estimate of 500Mt @ 1,139ppm Li for 3.03Mt contained
LCE (at a 700ppm Li cut-off) includes ahigh-grade zone in the northof the project of 47.9Mt @2,193ppm
Li for 569kt contained LCE, at a 1,300ppm Li cut-off9
.
Scoping leachability test-work on mineralised material from Red Mountain indicates high leachability
of lithium of up to 98%, varying with temperature, acid strength and leaching duration5
, and
beneficiation test-work has indicated the potential to upgrade the Red Mountain mineralisation1,2,8
. The
project has produced a high-purity (99.5%) battery-grade lithium carbonate directly from mineralised
rocks, with no third-party processing requirement19
.
The Red Mountain project is well-serviced by infrastructure, being located immediately adjacent to the
transcontinental Route 6, 20km west of a 525kV high-voltage transmission line and a 113-acre acre
private property with 592,000m3
.p.a of associated water rights secured only 6km from the Project7
.
5
newmurchgold.com.a
Figure 1. Location of Red Mountain and other Nevada Lithium projects.
6
newmurchgold.com.a
References
1 – ASX: ASE, 22 April 2025, Beneficiation testwork successfully upgrades mineralisation at Red Mountain
2 - ASX: ASE, 10 June 2025, Beneficiation Delivers 4,480ppm Lithium Clay Concentrate at Red Mountain
3 - NYSE: LAC, 31 December 2024, Updated NI 43-101 Technical Report for the Thacker Pass Project
4 - NASDAQ: ABAT, 4 September 2025, Tonopah Flats Lithium Project S-K 1300 Technical Report and Preliminary Feasibility Study
5 - ASX: ASE, 9 December 2024, Positive initial metallurgical results from Red Mountain
6 - ASX: ASE, 25 June 2025, Exceptional Drill-hole Intersects combined 170m of Lithium Mineralisation at Red Mountain
7 - ASX: VMS, 10 December 2025, Red Mountain Lithium Project De-Risked with Water Rights Secured
8 - ASX: VMS, 15 October 2025, Metallurgical test-work delivers 132% upgrade to lithium mineralisation at Red Mountain, Nevada
9 - ASX: VMS, 2 February 2026, Maiden Mineral Resource Estimate for the Red Mountain Lithium Project
10 - Lithium Carbonate Equivalent wt%(LCE) has been calculated from Lithium parts-per-million (ppm) by the formula LCE = Li (ppm)
x 5.323 /10,000
11 - IMARC Magnesium Sulfate Prices https://www.imarcgroup.com/magnesium-sulfate-pricing-report
12 - USGS Mineral Commodity Summary – Strontium 2026
13 - SMM, 27 April 2026, Battery-Grade Lithium Carbonate, USD/mt (https://www.metal.com/lithium/201102250059 )
14 - USGS Minerals Yearbook – Strontium 2019
15 – Epsomite wt% has been calculated from Magnesium wt% by the formula Epsomite (wt%) = Magnesium (wt%) x 10.136
16 - SMM, 27 April 2026, Strontium Carbonate, USD/mt (https://www.metal.com/lithium/202205010004)
18 - USGS Mineral Commodities Summary 2026
19 – ASX: VMS, 28 April 2026, Red Mountain produces Battery-grade Lithium product
20 - Global Trade Algorithmic Intelligence Center – Imports of Strontium Carbonate in USA https://gtaic.ai/market-
reports/strontium-carbonate-market-usa-report-in-2026
21 - https://finance.yahoo.com/news/magnesium-sulfate-market-volume-exceed-141100953.html
22 - Refer section 8.8 ASX:VMS, 26 April 2026, Appendix 5B
Authorisation
This announcement has been authorised for release by the Board of Venari Minerals NL.
Join the Venari Minerals Investor Hub
Engage with Venari Minerals through accessing reports, presentations, interviews
and other Company content. Ask Questions and browse responses to other
investors’ questions. Click here and follow the prompts to sign up.
For further information, please contact:
Matthew Healy Nicholas Read
Executive Director & CEO Media & Investor Relations
T: +61 (0) 431 683 952 T: +61 (0) 419 929 046
E: matt@venariminerals.com E: nicholas@readcorporate.com.au
Competent Persons
The information in this report that relates to Sampling Techniques and Data (Section 1) is based on
information compiled by Mr. Matthew Healy, a Competent Person who is a Member of The Australasian
Institute of Mining and Metallurgy (AusIMM Member number 303597). Mr Healy is a full-time employee
7
newmurchgold.com.a
of Venari Minerals NL and is eligible to participate in share-based incentive schemes of the Company.
Mr Healy has sufficient experience that is relevant to the style of mineralisation and type of deposit
under consideration and to the activity being undertaken to qualify as a Competent Person as defined
in the 2012 Edition of the ‘Australasian Code for Reporting of Exploration Results, Mineral Resources
and Ore Reserves’. Mr Healy consents to the inclusion in the report of the matters based on his
information in the form and context in which it appears.
The information in this report that relates to Reporting of Exploration Results (Section 2) and Mineral
Resource Estimates is based on information compiled by Mr. Richard Newport, principal partner of
Richard Newport & Associates – Consultant Geoscientists. Mr. Newport is a member of the Australian
Institute of Geoscientists and has sufficient experience which is relevant to the style of mineralisation
and type of deposit under consideration and to the activity which he is undertaking to qualify as a
Competent Person under the 2012 Edition of the ’Australasian Code for Reporting of Exploration
Results, Mineral Resources and Ore Reserves‘. Mr. Newport consents to the inclusion in this
announcement of the matters based on his information in the form and context in which it appears.
Mineral Resource Estimates
Where the Company references previously disclosed Mineral Resource Estimates it confirms that the
relevant JORC Table 1 disclosures are included with the original referenced ASX Announcements and
that it is not aware of any new information or data that materially affects the information included in
those ASX Announcements and in the case of Mineral Resources, that all material assumptions and
technical parameters underpinning the estimates in the Announcements continue to apply and have
not materially changed (Table 6).
Area Category Tonnes (Mt) Li (ppm) LCE (%) LCE (Mt)
North Inferred 91.6 1,618 0.86% 0.79
Central Inferred 408 1,031 0.55% 2.24
TOTAL Inferred 500 1,139 0.61% 3.03
Table 1. Red Mountain maiden MRE at the preferred reporting cut-off grade of 700ppm Li.
MRE reported under a range of cut-off grades in the original 2 February 2026 ASX Announcement.